Energy Projects Near You

Solar, wind and battery projects near Hunstanton (PE36)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE36 (King's Lynn and West Norfolk): 3 approved but not yet running. The largest live scheme is Sedgeford Hall Estate Solar Panels & Battery Storage (21 MW solar farm, approved on 23 August 2023, not yet built), 7.1 km away. Offshore, 8 wind farms are recorded within 40 km; the nearest is Westermost Rough A (210 MW, operational), 17.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
0awaiting a decision
3approved, not running
0operational

Projects within 10 km of PE36

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Thornham Solar Farmsolar farmsolar farm15abandonedupdated Apr 2015Jan 2013granted Apr 2013Apr 2015King's Lynn and West Norfolk5.2
Choseley Farmwind farmwind farm1.8application withdrawnupdated Nov 2005——Nov 2005King's Lynn and West Norfolk5.6
Sedgefordwind farmwind farm10.8application withdrawnupdated Nov 2005——Nov 2005King's Lynn and West Norfolk6.2
Snettisham Solar Farmsolar farmsolar farm2.5abandonedupdated Mar 2017Aug 2015granted Nov 2015Mar 2017King's Lynn and West Norfolk7.0
Sedgeford Hall Estate Solar Panels & Battery Storagesolar farmsolar farm21approved, not builtupdated May 2022Apr 2022granted Aug 2023May 2022King's Lynn and West Norfolk7.1
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Long Acres Holiday Park, South Beach Roadrooftop solarrooftop solar—approved, not builtupdated Apr 2025Feb 2025granted Mar 2025Apr 2025King's Lynn and West Norfolk4.4
Sedgeford Hall Estate Solar Panels & Battery Storagebattery storagebattery storage—approved, not builtupdated May 2022Apr 2022granted Aug 2023May 2022King's Lynn and West Norfolk7.1

Distance from the average position of the PE36 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm3010021
Rooftop solar101000
Wind farm200000
Battery storage101000

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Westermost Rough A210operationalupdated Apr 201817.9
Dudgeon East402operationalupdated Jan 202021.0
Lynn97.2operationalupdated Aug 201722.1
Race Bank (Phase 1)290operationalupdated Aug 202022.5
Race Bank (Phase 2)284operationalupdated Aug 202022.5
Centrica (Lincs)270operationalupdated May 201827.2
Inner Dowsing97.2operationalupdated Aug 201727.9
Triton Knoll857operationalupdated Mar 202238.4

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How King's Lynn and West Norfolk decides solar, wind and battery applications

ApplicationsKing's Lynn and West NorfolkUK
Decided applications (solar, wind, battery)6010,236
Refused11 (18%)19%
Solar refused5 of 3812%
Onshore wind refused3 of 645%
Battery storage refused3 of 1616%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed7 / 8—

All projects in King's Lynn and West Norfolk

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.