Energy Projects Near You

Solar, wind and battery projects near Walsingham (NR22)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NR22 (North Norfolk): 2 approved but not yet running, 3 operational. The largest live scheme is Helhoughton Road, Hempton (0.9 MW rooftop solar, approved on 8 August 2023, not yet built), 8.6 km away. Offshore, 9 wind farms are recorded within 40 km; the nearest is Dudgeon East (402 MW, operational), 29.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
0awaiting a decision
2approved, not running
3operational

Projects within 10 km of NR22

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
North Creake Airfieldsolar farmsolar farm20operationalupdated Aug 2014Feb 2013granted Mar 2013Aug 2014North Norfolk2.6
Snettisham Solar Farmsolar farmsolar farm2.7operationalupdated Jun 2017Oct 2014granted Mar 2016Jun 2017North Norfolk4.8
South Creake Solar Farmsolar farmsolar farm26operationalupdated Aug 2016Mar 2013granted Jun 2013Aug 2016King's Lynn and West Norfolk7.2
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bunkers Hill, Wells Roadrooftop solarrooftop solar0.4approved, not builtupdated Jun 2026Apr 2026granted Apr 2026Jun 2026North Norfolk2.7
Helhoughton Road, Hemptonrooftop solarrooftop solar0.9approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023North Norfolk8.6
Hempton Poultry Sheds, Hempton Roadrooftop solarrooftop solar0.5application withdrawnupdated Sep 2023Jul 2023—Sep 2023North Norfolk8.8

Distance from the average position of the NR22 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm300300
Rooftop solar302001.3

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Dudgeon East402operationalupdated Jan 202029.9
Westermost Rough A210operationalupdated Apr 201830.4
Race Bank (Phase 1)290operationalupdated Aug 202032.6
Race Bank (Phase 2)284operationalupdated Aug 202032.6
Sheringham Shoal317operationalupdated Nov 201932.8
Triton Knoll857operationalupdated Mar 202235.4
Sheringham Extension Project317approved, not builtupdated Jan 202435.5
Dudgeon Extension Project402approved, not builtupdated Jan 202435.5
Lynn97.2operationalupdated Aug 201738.5

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How North Norfolk decides solar, wind and battery applications

ApplicationsNorth NorfolkUK
Decided applications (solar, wind, battery)3610,236
Refused4 (11%)19%
Solar refused2 of 2912%
Onshore wind refused2 of 245%
Battery storage refused0 of 516%
Median time from submission to decision13.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in North Norfolk

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.