Dudgeon Extension Project offshore wind farm

Dudgeon Extension Project is a 402 MW offshore wind farm with 34 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 18 April 2024, not yet built; the record was last updated on 11 January 2024. Its REPD grid reference is 23 km from the nearest postcode on land (NR25 7EZ, North Norfolk). As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010109).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

402 MWoffshore wind farm
approved, not builtstatus in REPD
11 January 2024record last updated
23 km from land (North Norfolk)REPD location

Consent timeline

DateStage
5 September 2022Application submitted
18 April 2024Development consent granted (Secretary of State)

Project details

Technology
offshore wind farm
Capacity
402 MW
Turbines
34
Turbine height
326 m
Status (REPD)
approved, not built
Record last updated
11 January 2024
Operator or applicant
Equinor
Consenting authority (REPD)
The Planning Inspectorate - National Infrastructure
Application reference
EN010109
Nearest postcode on land
NR25 7EZ (North Norfolk), 22.5 km from the REPD grid reference
Time to decision
84 weeks
REPD reference
7692

Official project record at the Planning Inspectorate

Who decides

As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010109). All Energy Secretary decisions on solar and wind farms.

Postcode districts within 40 km

Districtkm
Sheringham (NR26)23.5
Cromer (NR27)26.2
Holt (NR25)26.4
Wells-Next-the-Sea (NR23)31.2
Melton Constable (NR24)33.5
Norwich (NR11)34.8
Walsingham (NR22)35.5
North Walsham (NR28)39.0

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Sheringham Extension Project317approved, not built<0.1
Sheringham Shoal317operational2.9
Triton Knoll857operational22.6
Cromer108abandoned23.2
Docking Shoal A540refused24.4

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (53.1493, 1.1843).