Energy Projects Near You

Sheringham Shoal offshore wind farm

Sheringham Shoal is a 317 MW offshore wind farm with 88 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 October 2012; the record was last updated on 5 November 2019. Its REPD grid reference is 21 km from the nearest postcode on land (NR25 7XF, North Norfolk). It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

How it works ↓

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

317 MWoffshore wind farm
operationalstatus in REPD
5 November 2019record last updated
21 km from land (North Norfolk)REPD location

Consent timeline

DateStage
30 May 2006Application submitted
7 August 2008Section 36 consent granted (Secretary of State)
30 June 2009Construction started
29 October 2012Operational

Project details

Technology
offshore wind farm
Capacity
317 MW
Turbines
88
Turbine capacity
3.6 MW
Status (REPD)
operational
Record last updated
5 November 2019
Operator or applicant
Equinor
Consenting authority (REPD)
DECC (S36)
Application reference
not recorded
Nearest postcode on land
NR25 7XF (North Norfolk), 20.8 km from the REPD grid reference
Time to decision
114 weeks
REPD reference
2512

Who decides

It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Postcode districts within 40 km

Districtkm
Sheringham (NR26)22.2
Holt (NR25)24.3
Cromer (NR27)25.6
Wells-Next-the-Sea (NR23)28.4
Melton Constable (NR24)31.4
Walsingham (NR22)32.8
Norwich (NR11)33.8
Fakenham (NR21)38.2
North Walsham (NR28)38.6

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Sheringham Extension Project317approved, not built2.9
Dudgeon Extension Project402approved, not built2.9
Triton Knoll857operational20.9
Docking Shoal A540refused22.2
Cromer108abandoned24.1

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (53.1353, 1.1479).

Sheringham Shoal, at 317 MW, has been operational since autumn 2012, and two extensions have been approved nearby, each no smaller than the farm itself. The wind farm of 88 turbines at 3.6 MW stands in the North Sea off North Norfolk, operated by Equinor. Its REPD point sits 21 km from the nearest postcode, with the postcode districts NR26 (Sheringham) and NR25 (Holt) at 22.2 and 24.3 km.

How it was approved and built

The application was submitted on 30 May 2006, and Section 36 consent was granted on 7 August 2008, after 114 weeks; the register names DECC as the authority, then the energy ministry. Construction ran from 30 June 2009 to 29 October 2012.

Approved, refused, abandoned

At 2.9 km, Sheringham Extension Project at 317 MW and Dudgeon Extension Project at 402 MW are approved, not built. Further out, Triton Knoll at 857 MW is operational. Docking Shoal A at 540 MW received a refusal, one of 3 among 109 offshore projects, while Cromer at 108 MW was abandoned. The Sheringham Shoal record was last updated on 5 November 2019, with stages given as of the July 2026 extract.