Westermost Rough A offshore wind farm

Westermost Rough A is a 210 MW offshore wind farm with 35 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 May 2015; the record was last updated on 5 April 2018. Its REPD grid reference is 15 km from the nearest postcode on land (PE31 8AX, King's Lynn and West Norfolk). It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

210 MWoffshore wind farm
operationalstatus in REPD
5 April 2018record last updated
15 km from land (King's Lynn and West Norfolk)REPD location

Consent timeline

DateStage
17 November 2009Application submitted
29 November 2011Section 36 consent granted (Secretary of State)
28 February 2014Construction started
26 May 2015Operational

Project details

Technology
offshore wind farm
Capacity
210 MW
Turbines
35
Turbine capacity
6 MW
Status (REPD)
operational
Record last updated
5 April 2018
Operator or applicant
Orsted (formerly Dong Energy)
Consenting authority (REPD)
DECC (S36)
Application reference
not recorded
Nearest postcode on land
PE31 8AX (King's Lynn and West Norfolk), 14.6 km from the REPD grid reference
Time to decision
106 weeks
REPD reference
2545

Who decides

It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Postcode districts within 40 km

Districtkm
Skegness (PE25)16.4
Hunstanton (PE36)17.9
Skegness (PE24)21.2
King's Lynn (PE31)24.0
Wells-Next-the-Sea (NR23)25.8
King's Lynn and West Norfolk (PE35)30.3
Walsingham (NR22)30.4
Alford (LN13)31.3
Mablethorpe (LN12)32.5
Spilsby (PE23)32.6
Fakenham (NR21)34.5
Boston (PE22)35.0

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Dudgeon East402operational4.1
Race Bank (Phase 1)290operational4.6
Race Bank (Phase 2)284operational4.6
Lynn97.2operational8.5
Centrica (Lincs)270operational10.5
Inner Dowsing97.2operational12.6
Docking Shoal A540refused18.8
Triton Knoll857operational23.7

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (53.0977, 0.5615).