Energy Projects Near You

Lynn offshore wind farm

Lynn is a 97.2 MW offshore wind farm with 27 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2008; the record was last updated on 24 August 2017. Its REPD grid reference is 7 km from the nearest postcode on land (PE25 3HH, East Lindsey). It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

97.2 MWoffshore wind farm
operationalstatus in REPD
24 August 2017record last updated
7 km from land (East Lindsey)REPD location

Consent timeline

DateStage
29 October 2003Application submitted
14 August 2004Section 36 consent granted (Secretary of State)
1 March 2008Construction started
15 March 2008Operational

Project details

Technology
offshore wind farm
Capacity
97.2 MW
Turbines
27
Turbine capacity
3.6 MW
Status (REPD)
operational
Record last updated
24 August 2017
Operator or applicant
XceCo
Consenting authority (REPD)
DECC (S36)
Application reference
not recorded
Nearest postcode on land
PE25 3HH (East Lindsey), 7.1 km from the REPD grid reference
Time to decision
41 weeks
REPD reference
2493

Who decides

It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Postcode districts within 40 km

Districtkm
Skegness (PE25)8.1
Skegness (PE24)12.9
Hunstanton (PE36)22.1
Alford (LN13)22.9
Spilsby (PE23)24.5
Mablethorpe (LN12)24.9
Boston (PE22)28.9
King's Lynn (PE31)29.3
Wells-Next-the-Sea (NR23)34.2
King's Lynn and West Norfolk (PE35)34.5
Boston (PE21)36.5
Walsingham (NR22)38.5

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Inner Dowsing97.2operational5.8
Centrica (Lincs)270operational6.2
Westermost Rough A210operational8.5
Race Bank (Phase 1)290operational9.2
Race Bank (Phase 2)284operational9.2
Dudgeon East402operational11.0
Docking Shoal A540refused24.7
Humber Gateway A219operational28.2

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (53.1356, 0.4515).