Humber Gateway A offshore wind farm

Humber Gateway A is a 219 MW offshore wind farm with 73 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 May 2015; the record was last updated on 3 October 2016. Its REPD grid reference is 16 km from the nearest postcode on land (LN12 2PE, East Lindsey). It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

219 MWoffshore wind farm
operationalstatus in REPD
3 October 2016record last updated
16 km from land (East Lindsey)REPD location

Consent timeline

DateStage
1 April 2008Application submitted
9 February 2011Section 36 consent granted (Secretary of State)
30 August 2013Construction started
30 May 2015Operational

Project details

Technology
offshore wind farm
Capacity
219 MW
Turbines
73
Turbine capacity
3 MW
Status (REPD)
operational
Record last updated
3 October 2016
Operator or applicant
E.ON Humber Wind Ltd/ Balfour Beatty Investments and Equitix.
Consenting authority (REPD)
DECC (S36)
Application reference
not recorded
Nearest postcode on land
LN12 2PE (East Lindsey), 16.4 km from the REPD grid reference
Time to decision
149 weeks
REPD reference
2544

Who decides

It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Postcode districts within 40 km

Districtkm
Mablethorpe (LN12)17.0
Alford (LN13)25.1
Skegness (PE25)28.2
Skegness (PE24)29.3
Louth (LN11)31.5
Spilsby (PE23)36.3
Grimsby (DN36)38.4

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Inner Dowsing97.2operational22.5
Centrica (Lincs)270operational22.6
Lynn97.2operational28.2
Race Bank (Phase 1)290operational28.6
Race Bank (Phase 2)284operational28.6

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (53.3875, 0.5006).