Energy Projects Near You

Inner Dowsing offshore wind farm

Inner Dowsing is a 97.2 MW offshore wind farm with 27 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 April 2008; the record was last updated on 24 August 2017. Its REPD grid reference is 6 km from the nearest postcode on land (PE25 1JZ, East Lindsey). It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

97.2 MWoffshore wind farm
operationalstatus in REPD
24 August 2017record last updated
6 km from land (East Lindsey)REPD location

Consent timeline

DateStage
11 September 2002Application submitted
23 September 2003Section 36 consent granted (Secretary of State)
1 March 2008Construction started
20 April 2008Operational

Project details

Technology
offshore wind farm
Capacity
97.2 MW
Turbines
27
Turbine capacity
3.6 MW
Status (REPD)
operational
Record last updated
24 August 2017
Operator or applicant
XceCo
Consenting authority (REPD)
DECC (S36)
Application reference
not recorded
Nearest postcode on land
PE25 1JZ (East Lindsey), 6.2 km from the REPD grid reference
Time to decision
54 weeks
REPD reference
2491

Who decides

It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Postcode districts within 40 km

Districtkm
Skegness (PE25)8.4
Skegness (PE24)12.4
Alford (LN13)19.5
Mablethorpe (LN12)19.9
Spilsby (PE23)23.9
Hunstanton (PE36)27.9
Boston (PE22)31.0
Louth (LN11)34.7
King's Lynn (PE31)35.0
Horncastle (LN9)37.3
Wells-Next-the-Sea (NR23)38.2
Boston (PE21)39.4

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Centrica (Lincs)270operational3.5
Lynn97.2operational5.8
Race Bank (Phase 1)290operational11.1
Race Bank (Phase 2)284operational11.1
Westermost Rough A210operational12.6
Dudgeon East402operational13.6
Humber Gateway A219operational22.5
Docking Shoal A540refused25.0

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (53.188, 0.4465).