Energy Projects Near You

Solar, wind and battery projects near Mablethorpe (LN12)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LN12 (East Lindsey): 1 approved but not yet running, 3 operational. The largest live scheme is Strubby Airfield, Alford Road (0.2 MW rooftop solar, approved on 14 February 2024, not yet built), 7.7 km away. Offshore, 8 wind farms are recorded within 40 km; the nearest is Humber Gateway A (219 MW, operational), 17.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
0awaiting a decision
1approved, not running
3operational

Projects within 10 km of LN12

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bambers Farmwind farmwind farm9.6operationalupdated Dec 2009Feb 2003granted Jun 2003Dec 2009East Lindsey1.9
Bambers IIwind farmwind farm4.6operationalupdated Mar 2010May 2005granted Sep 2005Mar 2010East Lindsey1.9
Withernwind turbinewind turbine1.3refusedupdated Jan 2010Sep 2005refused Jun 2006Jan 2010East Lindsey5.8
Asserby wind farmwind farmwind farm10refusedupdated Jun 2015Jun 2014refused Jun 2015Jun 2015East Lindsey7.1
Gayton Le Marsh Wind Farmwind farmwind farm16.4operationalupdated Mar 2016Aug 2011granted Apr 2013Mar 2016East Lindsey7.5
Langham Wind Farmwind farmwind farm12refused on appealupdated Sep 2011Jan 2007refused Sep 2011Sep 2011East Lindsey9.3
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Strubby Airfield, Alford Roadrooftop solarrooftop solar0.2approved, not builtupdated Feb 2024Jan 2024granted Feb 2024Feb 2024East Lindsey7.7

Distance from the average position of the LN12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar101000.2
Wind farm500320
Wind turbine100010

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Humber Gateway A219operationalupdated Oct 201617.0
Inner Dowsing97.2operationalupdated Aug 201719.9
Centrica (Lincs)270operationalupdated May 201822.4
Lynn97.2operationalupdated Aug 201724.9
Race Bank (Phase 2)284operationalupdated Aug 202030.5
Race Bank (Phase 1)290operationalupdated Aug 202030.5
Westermost Rough A210operationalupdated Apr 201832.5
Dudgeon East402operationalupdated Jan 202033.1

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How East Lindsey decides solar, wind and battery applications

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

All projects in East Lindsey

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.