Langham Wind Farm (12 MW)
Langham Wind Farm is a 12 MW wind farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 29 September 2011; the record was last updated on 12 September 2011.
12 MWwind farm
refused on appealstatus in REPD
12 September 2011record last updated
East Lindseycouncil area
Planning timeline
| Date | Stage |
|---|---|
| 5 January 2007 | Application submitted |
| 29 September 2011 | Refused by the planning authority |
| 29 September 2011 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 12 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 12 September 2011
- Operator or applicant
- RWE Generation UK Plc
- Planning authority
- East Lindsey
- Planning application reference
- N/005/02812/06
- Appeal reference
- APP/D2510/10/2130539
- Turbines
- 6
- Address (REPD)
- Land between Anderby and Chapel St Leonards
- Council area (by location)
- East Lindsey
- Time to decision
- 247 weeks
- REPD reference
- 3442
Who decides
| Applications | East Lindsey | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 11 (22%) | 19% |
| Solar refused | 0 of 30 | 12% |
| Onshore wind refused | 11 of 15 | 45% |
| Battery storage refused | 0 of 4 | 16% |
| Median time from submission to decision | 17.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Asserby wind farm | wind farm | 10 | refused | 5.0 |
| Habertoft, Solar Farm South of Low Lane | solar farm | 10.4 | abandoned | 7.1 |
| Orby Windfarm | wind farm | 11.7 | refused | 7.9 |
| Bambers Farm | wind farm | 9.6 | operational | 9.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2497, 0.3067).