Energy Projects Near You

Langham Wind Farm (12 MW)

Langham Wind Farm is a 12 MW wind farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 29 September 2011; the record was last updated on 12 September 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
refused on appealstatus in REPD
12 September 2011record last updated
East Lindseycouncil area

Planning timeline

DateStage
5 January 2007Application submitted
29 September 2011Refused by the planning authority
29 September 2011Appeal refused

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
refused on appeal
Record last updated
12 September 2011
Operator or applicant
RWE Generation UK Plc
Planning authority
East Lindsey
Planning application reference
N/005/02812/06
Appeal reference
APP/D2510/10/2130539
Turbines
6
Address (REPD)
Land between Anderby and Chapel St Leonards
Council area (by location)
East Lindsey
Time to decision
247 weeks
REPD reference
3442

Who decides

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Asserby wind farmwind farm10refused5.0
Habertoft, Solar Farm South of Low Lanesolar farm10.4abandoned7.1
Orby Windfarmwind farm11.7refused7.9
Bambers Farmwind farm9.6operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.2497, 0.3067).