Orby Windfarm (11.7 MW)

Orby Windfarm is an 11.7 MW wind farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 18 March 2011; the record was last updated on 1 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.7 MWwind farm
refusedstatus in REPD
1 April 2015record last updated
East Lindseycouncil area

Planning timeline

DateStage
24 March 2010Application submitted
18 March 2011Refused by the planning authority
28 October 2011Appeal lodged
30 March 2015Secretary of State refused

Project details

Technology
wind farm
Capacity
11.7 MW
Status (REPD)
refused
Record last updated
1 April 2015
Operator or applicant
Mark Caudwell Ltd
Planning authority
East Lindsey
Planning application reference
N/084/00642/10
Appeal reference
APP/D2510/A/11/2161066
Turbines
9
Address (REPD)
Orby Marsh Lane, Hogsthorpe, Skegness
Council area (by location)
East Lindsey
Time to decision
51 weeks
REPD reference
4406

Earlier applications for this site

ApplicationMWSubmittedOutcome
Orby Windfarm N/84/2334/05546 December 2002withdrawn 25 June 2008
Orby Windfarm 134/2016/02306 December 2002refused 5 June 2003

Who decides

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Habertoft, Solar Farm South of Low Lanesolar farm10.4abandoned1.1
The Hollies Solar Park - Skegnesssolar farm8.6operational4.4
The Holliesbattery storage24permission expired4.7
Bank House Farmwind farm12application withdrawn5.3
Lincoln Farmsolar farm11.4operational6.2
Manor Farm Energy Storagebattery storage10approved, not built6.3
Bicker Fen (previously Manor Farm)solar farm22.6operational6.3
Langham Wind Farmwind farm12refused on appeal7.9
Asserby wind farmwind farm10refused9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1835, 0.2656).