Bicker Fen (previously Manor Farm) (22.6 MW solar farm)

Bicker Fen (previously Manor Farm) is a 22.6 MW solar farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 12 March 2024; the record was last updated on 18 March 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22.6 MWsolar farm
operationalstatus in REPD
18 March 2024record last updated
East Lindseycouncil area

Planning timeline

DateStage
2 May 2017Application submitted
30 November 2017Planning permission granted
12 March 2024Operational

Project details

Technology
solar farm
Capacity
22.6 MW
Status (REPD)
operational
Record last updated
18 March 2024
Operator or applicant
Innova Renewables Limited
Planning authority
East Lindsey
Planning application reference
S/051/00772/17
Site area
34.1 ha
Address (REPD)
Manor Farm, Wainfleet Road, Irby-in-the-Marsh, Skegness
Council area (by location)
East Lindsey
Time to decision
30 weeks
Contracts for Difference
AR4
REPD reference
1694

Recorded together with Manor Farm Energy Storage (10 MW battery storage, approved, not built).

Who decides

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lincoln Farmsolar farm11.4operational0.9
The Hollies Solar Park - Skegnesssolar farm8.6operational2.9
The Holliesbattery storage24permission expired3.3
Bank House Farmwind farm12application withdrawn4.4
Low Farm Solar Farmsolar farm49.9under construction5.4
Wainfleet Wind Farmwind farm12application withdrawn5.9
Orby Windfarmwind farm11.7refused6.3
Habertoft, Solar Farm South of Low Lanesolar farm10.4abandoned6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1475, 0.1918).