Energy Projects Near You

Solar, wind and battery projects near Spilsby (PE23)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE23 (East Lindsey): 1 is waiting for a planning decision, 1 approved but not yet running, 2 operational. The largest live scheme is Manor Farm Energy Storage (10 MW battery storage, approved on 30 November 2017, not yet built; REPD status may be out of date), 7.4 km away. Offshore, 8 wind farms are recorded within 40 km; the nearest is Inner Dowsing (97.2 MW, operational), 23.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
1awaiting a decision
1approved, not running
2operational

Projects within 10 km of PE23

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bicker Fen (previously Manor Farm)solar farmsolar farm22.6operationalupdated Mar 2024May 2017granted Nov 2017Mar 2024East Lindsey7.4
Manor Farm Energy Storagebattery storagebattery storage10approved, not built may be out of dateupdated Dec 2022May 2017granted Nov 2017Dec 2022East Lindsey7.4
Lincoln Farmsolar farmsolar farm11.4operationalupdated Jul 2016Mar 2014granted Oct 2014Jul 2016East Lindsey8.3
Bluestone Heath Roadsolar farmsolar farm1.5permission expiredupdated Aug 2020Feb 2015granted Mar 2015Aug 2020East Lindsey8.8
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ulceby Grange Farm, Church Lanewind turbinewind turbine0.5application submittedupdated May 2026Apr 2026—May 2026East Lindsey7.6

Distance from the average position of the PE23 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm300200
Wind turbine110000.5
Battery storage1010010

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Inner Dowsing97.2operationalupdated Aug 201723.9
Lynn97.2operationalupdated Aug 201724.5
Centrica (Lincs)270operationalupdated May 201827.3
Westermost Rough A210operationalupdated Apr 201832.6
Race Bank (Phase 2)284operationalupdated Aug 202033.6
Race Bank (Phase 1)290operationalupdated Aug 202033.6
Dudgeon East402operationalupdated Jan 202035.5
Humber Gateway A219operationalupdated Oct 201636.3

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How East Lindsey decides solar, wind and battery applications

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

All projects in East Lindsey

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PE23, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.