Energy Projects Near You

Solar, wind and battery projects near Woodhall Spa (LN10)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LN10 (East Lindsey): 3 approved but not yet running, 1 operational. The largest live scheme is The Hub, Mareham Road - Ground Mounted Solar Panels (0.2 MW solar farm, approved on 3 October 2025, not yet built), 8.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
0awaiting a decision
3approved, not running
1operational

Projects within 10 km of LN10

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Grange Farm (Kirkby on Bain)solar farmsolar farm9operationalupdated Apr 2015Jul 2014granted Sep 2014Apr 2015East Lindsey4.1
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Campney Grange, Bucknallrooftop solarrooftop solar0.2approved, not builtupdated May 2022Apr 2022granted Feb 2023May 2022East Lindsey5.0
Chandlers Farm Equipment, Boston Roadbattery storagebattery storage0.2approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026East Lindsey8.3
The Hub, Mareham Road - Ground Mounted Solar Panelssolar farmsolar farm0.2approved, not builtupdated Oct 2025Oct 2025granted Oct 2025Oct 2025East Lindsey8.9

Distance from the average position of the LN10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm201100.2
Rooftop solar101000.2
Battery storage101000.2

MW in pipeline: pending, approved and under-construction capacity.

How East Lindsey decides solar, wind and battery applications

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

All projects in East Lindsey

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.