Energy Projects Near You

Solar, wind and battery projects near Skegness (PE25)

14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE25 (East Lindsey): 5 approved but not yet running, 5 operational. The largest live scheme is Manor Farm Energy Storage (10 MW battery storage, approved on 30 November 2017, not yet built; REPD status may be out of date), 9.5 km away. Offshore, 9 wind farms are recorded within 40 km; the nearest is Lynn (97.2 MW, operational), 8.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14projects within 10 km
0awaiting a decision
5approved, not running
5operational

Projects within 10 km of PE25

Projects of 1 MW and more (11)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Skegness Solar Parksolar farmsolar farm4.9operationalupdated May 2016Sep 2014granted Dec 2014May 2016East Lindsey2.5
Bank House Farmwind farmwind farm12application withdrawnupdated Sep 2015Jun 2012—Sep 2015East Lindsey5.6
Orby Windfarmwind farmwind farm11.7refusedupdated Apr 2015Mar 2010refused Mar 2011Apr 2015East Lindsey5.6
The Hollies Solar Park - Skegness - extensionsolar farmsolar farm1.4approved, not built may be out of dateupdated Feb 2020Sep 2013granted Dec 2013Feb 2020East Lindsey6.3
The Holliesbattery storagebattery storage24permission expiredupdated Feb 2020May 2017—Feb 2020East Lindsey6.3
The Hollieswind farmwind farm2.6operationalupdated Jan 2010Jul 2002granted Oct 2004Jan 2010East Lindsey6.3
Habertoft, Solar Farm South of Low Lanesolar farmsolar farm10.4abandonedupdated Sep 2018Jun 2015granted Sep 2015Sep 2018East Lindsey6.6
The Hollies Solar Park - Skegnesssolar farmsolar farm8.6operationalupdated Nov 2013Jun 2012granted Oct 2012Nov 2013East Lindsey6.6
Lincoln Farmsolar farmsolar farm11.4operationalupdated Jul 2016Mar 2014granted Oct 2014Jul 2016East Lindsey8.9
Bicker Fen (previously Manor Farm)solar farmsolar farm22.6operationalupdated Mar 2024May 2017granted Nov 2017Mar 2024East Lindsey9.5
Manor Farm Energy Storagebattery storagebattery storage10approved, not built may be out of dateupdated Dec 2022May 2017granted Nov 2017Dec 2022East Lindsey9.5
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
E & M Hames, Hawthorn Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024East Lindsey1.7
Southview Leisure Park, Burgh Roadrooftop solarrooftop solar0.4approved, not builtupdated Jul 2024May 2024granted Jun 2024Jul 2024East Lindsey1.7
Ingoldmells Road, Burgh Le Marshbattery storagebattery storage0.2approved, not builtupdated Jun 2026Nov 2025granted May 2026Jun 2026East Lindsey5.4

Distance from the average position of the PE25 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm601401.4
Rooftop solar202000.6
Wind farm300110
Battery storage3020010.2

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Lynn97.2operationalupdated Aug 20178.1
Inner Dowsing97.2operationalupdated Aug 20178.4
Centrica (Lincs)270operationalupdated May 201811.4
Westermost Rough A210operationalupdated Apr 201816.4
Race Bank (Phase 2)284operationalupdated Aug 202017.1
Race Bank (Phase 1)290operationalupdated Aug 202017.1
Dudgeon East402operationalupdated Jan 202019.1
Humber Gateway A219operationalupdated Oct 201628.2
Triton Knoll857operationalupdated Mar 202235.7

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How East Lindsey decides solar, wind and battery applications

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

All projects in East Lindsey

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PE25, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.