Solar, wind and battery projects near Skegness (PE25)
14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PE25 (East Lindsey): 5 approved but not yet running, 5 operational. The largest live scheme is Manor Farm Energy Storage (10 MW battery storage, approved on 30 November 2017, not yet built; REPD status may be out of date), 9.5 km away. Offshore, 9 wind farms are recorded within 40 km; the nearest is Lynn (97.2 MW, operational), 8.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of PE25
Projects of 1 MW and more (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Skegness Solar Parksolar farm | solar farm | 4.9 | operationalupdated May 2016 | Sep 2014 | granted Dec 2014 | May 2016 | East Lindsey | 2.5 |
| Bank House Farmwind farm | wind farm | 12 | application withdrawnupdated Sep 2015 | Jun 2012 | — | Sep 2015 | East Lindsey | 5.6 |
| Orby Windfarmwind farm | wind farm | 11.7 | refusedupdated Apr 2015 | Mar 2010 | refused Mar 2011 | Apr 2015 | East Lindsey | 5.6 |
| The Hollies Solar Park - Skegness - extensionsolar farm | solar farm | 1.4 | approved, not built may be out of dateupdated Feb 2020 | Sep 2013 | granted Dec 2013 | Feb 2020 | East Lindsey | 6.3 |
| The Holliesbattery storage | battery storage | 24 | permission expiredupdated Feb 2020 | May 2017 | — | Feb 2020 | East Lindsey | 6.3 |
| The Hollieswind farm | wind farm | 2.6 | operationalupdated Jan 2010 | Jul 2002 | granted Oct 2004 | Jan 2010 | East Lindsey | 6.3 |
| Habertoft, Solar Farm South of Low Lanesolar farm | solar farm | 10.4 | abandonedupdated Sep 2018 | Jun 2015 | granted Sep 2015 | Sep 2018 | East Lindsey | 6.6 |
| The Hollies Solar Park - Skegnesssolar farm | solar farm | 8.6 | operationalupdated Nov 2013 | Jun 2012 | granted Oct 2012 | Nov 2013 | East Lindsey | 6.6 |
| Lincoln Farmsolar farm | solar farm | 11.4 | operationalupdated Jul 2016 | Mar 2014 | granted Oct 2014 | Jul 2016 | East Lindsey | 8.9 |
| Bicker Fen (previously Manor Farm)solar farm | solar farm | 22.6 | operationalupdated Mar 2024 | May 2017 | granted Nov 2017 | Mar 2024 | East Lindsey | 9.5 |
| Manor Farm Energy Storagebattery storage | battery storage | 10 | approved, not built may be out of dateupdated Dec 2022 | May 2017 | granted Nov 2017 | Dec 2022 | East Lindsey | 9.5 |
Smaller schemes under 1 MW, mostly rooftop solar (3)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| E & M Hames, Hawthorn Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 | East Lindsey | 1.7 |
| Southview Leisure Park, Burgh Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jul 2024 | May 2024 | granted Jun 2024 | Jul 2024 | East Lindsey | 1.7 |
| Ingoldmells Road, Burgh Le Marshbattery storage | battery storage | 0.2 | approved, not builtupdated Jun 2026 | Nov 2025 | granted May 2026 | Jun 2026 | East Lindsey | 5.4 |
Distance from the average position of the PE25 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 6 | 0 | 1 | 4 | 0 | 1.4 |
| Rooftop solar | 2 | 0 | 2 | 0 | 0 | 0.6 |
| Wind farm | 3 | 0 | 0 | 1 | 1 | 0 |
| Battery storage | 3 | 0 | 2 | 0 | 0 | 10.2 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Lynn | 97.2 | operationalupdated Aug 2017 | 8.1 |
| Inner Dowsing | 97.2 | operationalupdated Aug 2017 | 8.4 |
| Centrica (Lincs) | 270 | operationalupdated May 2018 | 11.4 |
| Westermost Rough A | 210 | operationalupdated Apr 2018 | 16.4 |
| Race Bank (Phase 2) | 284 | operationalupdated Aug 2020 | 17.1 |
| Race Bank (Phase 1) | 290 | operationalupdated Aug 2020 | 17.1 |
| Dudgeon East | 402 | operationalupdated Jan 2020 | 19.1 |
| Humber Gateway A | 219 | operationalupdated Oct 2016 | 28.2 |
| Triton Knoll | 857 | operationalupdated Mar 2022 | 35.7 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How East Lindsey decides solar, wind and battery applications
| Applications | East Lindsey | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 11 (22%) | 19% |
| Solar refused | 0 of 30 | 12% |
| Onshore wind refused | 11 of 15 | 45% |
| Battery storage refused | 0 of 4 | 16% |
| Median time from submission to decision | 17.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 3 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PE25, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.