Bank House Farm (12 MW wind farm)

Bank House Farm is a 12 MW wind farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 3 August 2015; the record was last updated on 2 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
application withdrawnstatus in REPD
2 September 2015record last updated
East Lindseycouncil area

Planning timeline

DateStage
29 June 2012Application submitted
3 August 2015Application withdrawn

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
application withdrawn
Record last updated
2 September 2015
Operator or applicant
REG Windpower
Planning authority
East Lindsey
Planning application reference
S/039/01184/12
Turbines
6
Address (REPD)
Croft, Lincolnshire
Council area (by location)
East Lindsey
REPD reference
4180

Who decides

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
The Holliesbattery storage24permission expired1.3
The Hollies Solar Park - Skegnesssolar farm8.6operational1.9
Lincoln Farmsolar farm11.4operational3.6
Manor Farm Energy Storagebattery storage10approved, not built4.4
Bicker Fen (previously Manor Farm)solar farm22.6operational4.4
Orby Windfarmwind farm11.7refused5.3
Habertoft, Solar Farm South of Low Lanesolar farm10.4abandoned6.3
Low Farm Solar Farmsolar farm49.9under construction6.5
Wainfleet Wind Farmwind farm12application withdrawn7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1361, 0.2554).