Manor Farm Energy Storage (10 MW)

Manor Farm Energy Storage is a 10 MW battery storage project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 November 2017, not yet built; the record was last updated on 15 December 2022. REPD also records that the planning permission expired on 30 November 2020, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWbattery storage
approved, not builtmay be out of datestatus in REPD
15 December 2022record last updated
East Lindseycouncil area

REPD also records that the planning permission expired on 30 November 2020, so the project may not go ahead in this form.

Planning timeline

DateStage
2 May 2017Application submitted
30 November 2017Planning permission granted
30 November 2020Permission expired

Project details

Technology
battery storage (co-located with re)
Capacity
10 MW
Status (REPD)
approved, not built
Record last updated
15 December 2022
Operator or applicant
Innova Renewables Limited
Planning authority
East Lindsey
Planning application reference
S/051/00772/17
Address (REPD)
Manor Farm, Wainfleet Road, Irby-in-the-Marsh, Skegness
Council area (by location)
East Lindsey
Time to decision
30 weeks
REPD reference
6948

Recorded together with Bicker Fen (previously Manor Farm) (22.6 MW solar farm, operational).

Who decides

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lincoln Farmsolar farm11.4operational0.9
The Hollies Solar Park - Skegnesssolar farm8.6operational2.9
The Holliesbattery storage24permission expired3.3
Bank House Farmwind farm12application withdrawn4.4
Low Farm Solar Farmsolar farm49.9under construction5.4
Wainfleet Wind Farmwind farm12application withdrawn5.9
Orby Windfarmwind farm11.7refused6.3
Habertoft, Solar Farm South of Low Lanesolar farm10.4abandoned6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1475, 0.1918).