Habertoft, Solar Farm South of Low Lane (10.4 MW)
Habertoft, Solar Farm South of Low Lane is a 10.4 MW solar farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 17 September 2018.
10.4 MWsolar farm
abandonedstatus in REPD
17 September 2018record last updated
East Lindseycouncil area
Planning timeline
| Date | Stage |
|---|---|
| 9 June 2015 | Application submitted |
| 3 September 2015 | Planning permission granted |
| 3 September 2018 | Permission expired |
Project details
- Technology
- solar farm
- Capacity
- 10.4 MW
- Status (REPD)
- abandoned
- Record last updated
- 17 September 2018
- Operator or applicant
- Lark Energy
- Planning authority
- East Lindsey
- Planning application reference
- S/208/01064/15
- Site area
- 19.8 ha
- Address (REPD)
- Land south of, Habertoft Lane, Habertoft, Alford
- Council area (by location)
- East Lindsey
- Time to decision
- 12 weeks
- REPD reference
- 5260
Who decides
| Applications | East Lindsey | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 11 (22%) | 19% |
| Solar refused | 0 of 30 | 12% |
| Onshore wind refused | 11 of 15 | 45% |
| Battery storage refused | 0 of 4 | 16% |
| Median time from submission to decision | 17.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Orby Windfarm | wind farm | 11.7 | refused | 1.1 |
| The Hollies Solar Park - Skegness | solar farm | 8.6 | operational | 5.2 |
| The Hollies | battery storage | 24 | permission expired | 5.5 |
| Bank House Farm | wind farm | 12 | application withdrawn | 6.3 |
| Lincoln Farm | solar farm | 11.4 | operational | 6.7 |
| Bicker Fen (previously Manor Farm) | solar farm | 22.6 | operational | 6.7 |
| Manor Farm Energy Storage | battery storage | 10 | approved, not built | 6.7 |
| Langham Wind Farm | wind farm | 12 | refused on appeal | 7.1 |
| Asserby wind farm | wind farm | 10 | refused | 8.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1927, 0.2583).