Energy Projects Near You

Centrica (Lincs) offshore wind farm

Centrica (Lincs) is a 270 MW offshore wind farm with 75 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 July 2013; the record was last updated on 1 May 2018. Its REPD grid reference is 10 km from the nearest postcode on land (PE25 1JZ, East Lindsey). It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

270 MWoffshore wind farm
operationalstatus in REPD
1 May 2018record last updated
10 km from land (East Lindsey)REPD location

Consent timeline

DateStage
24 January 2007Application submitted
21 October 2008Section 36 consent granted (Secretary of State)
1 March 2010Construction started
24 July 2013Operational

Project details

Technology
offshore wind farm
Capacity
270 MW
Turbines
75
Turbine capacity
3.6 MW
Status (REPD)
operational
Record last updated
1 May 2018
Operator or applicant
Ørsted
Consenting authority (REPD)
DECC (S36)
Application reference
not recorded
Nearest postcode on land
PE25 1JZ (East Lindsey), 9.7 km from the REPD grid reference
Time to decision
91 weeks
REPD reference
2513

Who decides

It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Postcode districts within 40 km

Districtkm
Skegness (PE25)11.4
Skegness (PE24)15.7
Mablethorpe (LN12)22.4
Alford (LN13)22.8
Hunstanton (PE36)27.2
Spilsby (PE23)27.3
Boston (PE22)33.8
King's Lynn (PE31)34.0
Wells-Next-the-Sea (NR23)35.5
Louth (LN11)37.8
King's Lynn and West Norfolk (PE35)39.7

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Inner Dowsing97.2operational3.5
Lynn97.2operational6.2
Race Bank (Phase 1)290operational8.1
Race Bank (Phase 2)284operational8.1
Westermost Rough A210operational10.5
Dudgeon East402operational10.7
Docking Shoal A540refused21.5
Humber Gateway A219operational22.6

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (53.1842, 0.4981).