Solar, wind and battery projects near Louth (LN11)
11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LN11 (East Lindsey): 1 is waiting for a planning decision, 4 approved but not yet running, 5 operational. The largest live scheme is Solar Panels at North & S/O Lincoln Gate (98 MW solar farm, application submitted on 15 April 2026, no decision recorded), 8.9 km away. Offshore, 4 wind farms are recorded within 40 km; the nearest is Humber Gateway A (219 MW, operational), 31.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of LN11
Projects of 1 MW and more (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Yarburgh Grove Farmsolar farm | solar farm | 8.1 | operationalupdated Sep 2018 | May 2014 | granted Oct 2014 | Sep 2018 | East Lindsey | 3.9 |
| Fen Farmwind farm | wind farm | 16 | operationalupdated Dec 2008 | Jul 2003 | granted Nov 2004 | Dec 2008 | East Lindsey | 6.3 |
| Fen Farm Solar Parksolar farm | solar farm | 1 | operationalupdated Jul 2011 | Aug 2010 | granted Nov 2010 | Jul 2011 | East Lindsey | 6.3 |
| Fen Farm Solar Park (extension)solar farm | solar farm | 5 | permission expiredupdated Aug 2020 | Dec 2015 | granted Mar 2016 | Aug 2020 | East Lindsey | 6.4 |
| Fen Farm Solar Parksolar farm | solar farm | 14 | approved, not builtupdated Mar 2025 | Apr 2024 | granted Aug 2024 | Mar 2025 | East Lindsey | 6.9 |
| High Leassolar farm | solar farm | 6.5 | operationalupdated Feb 2016 | Sep 2014 | granted Dec 2014 | Feb 2016 | East Lindsey | 7.5 |
| Solar Panels at North & S/O Lincoln Gatesolar farm | solar farm | 98 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | East Lindsey | 8.9 |
| Gayton Le Marsh Wind Farmwind farm | wind farm | 16.4 | operationalupdated Mar 2016 | Aug 2011 | granted Apr 2013 | Mar 2016 | East Lindsey | 9.4 |
Smaller schemes under 1 MW, mostly rooftop solar (3)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Meridan Leisure Centrerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2024 | Sep 2024 | granted Nov 2024 | Nov 2024 | East Lindsey | 1.6 |
| Micronclean, Lincoln Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2023 | Mar 2023 | granted May 2023 | May 2023 | East Lindsey | 2.1 |
| Lincolnshire Rural Activity Centre, Kenwick Hillrooftop solar | rooftop solar | — | approved, not builtupdated Jun 2026 | Feb 2026 | granted Apr 2026 | Jun 2026 | East Lindsey | 4.2 |
Distance from the average position of the LN11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 6 | 1 | 1 | 3 | 0 | 112 |
| Rooftop solar | 3 | 0 | 3 | 0 | 0 | 0.7 |
| Wind farm | 2 | 0 | 0 | 2 | 0 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Humber Gateway A | 219 | operationalupdated Oct 2016 | 31.5 |
| Inner Dowsing | 97.2 | operationalupdated Aug 2017 | 34.7 |
| Centrica (Lincs) | 270 | operationalupdated May 2018 | 37.8 |
| Lynn | 97.2 | operationalupdated Aug 2017 | 38.7 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How East Lindsey decides solar, wind and battery applications
| Applications | East Lindsey | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 11 (22%) | 19% |
| Solar refused | 0 of 30 | 12% |
| Onshore wind refused | 11 of 15 | 45% |
| Battery storage refused | 0 of 4 | 16% |
| Median time from submission to decision | 17.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 3 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.