Solar, wind and battery projects near Grimsby (DN36)
37 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DN36 (North East Lincolnshire): 4 are waiting for a planning decision, 18 approved but not yet running, 7 operational. The largest live scheme is Solar Panels at North & S/O Lincoln Gate (98 MW solar farm, application submitted on 15 April 2026, no decision recorded), 8.2 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Humber Gateway A (219 MW, operational), 38.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of DN36
Projects of 1 MW and more (19)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Bishopthorpewind farm | wind farm | 16.4 | operationalupdated Apr 2017 | Oct 2012 | granted Mar 2015 | Apr 2017 | East Lindsey | 2.6 |
| Hewitts Avenue, New Walthambattery storage | battery storage | 49.9 | approved, not builtupdated May 2025 | Feb 2024 | granted Mar 2025 | May 2025 | North East Lincolnshire | 3.0 |
| Newton Marsh Wind Projectwind farm | wind farm | 4.6 | operationalupdated Apr 2014 | Jan 2008 | granted May 2009 | Apr 2014 | East Lindsey | 3.3 |
| Louth Canal Wind Farmwind farm | wind farm | 10 | refused on appealupdated Sep 2014 | Mar 2012 | refused Apr 2013 | Sep 2014 | East Lindsey | 4.3 |
| Fen Lane wind farmwind farm | wind farm | 17.5 | refused on appealupdated Oct 2017 | Jun 2014 | refused Oct 2017 | Oct 2017 | East Lindsey | 5.6 |
| Damwells Farmwind farm | wind farm | 10 | application withdrawnupdated Nov 2015 | Mar 2014 | — | Nov 2015 | East Lindsey | 6.4 |
| Low Farm Solar Arraysolar farm | solar farm | 20 | operationalupdated Jan 2024 | Jun 2015 | granted Oct 2015 | Jan 2024 | North East Lincolnshire | 6.6 |
| Bradley Road Solar Farmsolar farm | solar farm | 43.7 | approved, not builtupdated May 2024 | Nov 2023 | granted Apr 2024 | May 2024 | North East Lincolnshire | 6.7 |
| Bradley Roadbattery storage | battery storage | 10 | approved, not builtupdated May 2024 | Nov 2023 | granted Apr 2024 | May 2024 | North East Lincolnshire | 6.7 |
| Laceby Solar Farmsolar farm | solar farm | 27.1 | operationalupdated Jul 2016 | Mar 2015 | granted Jun 2015 | Jul 2016 | North East Lincolnshire | 7.2 |
| Gorton Street & Murray Street, Grimsby Dockssolar farm | solar farm | 1.5 | approved, not builtupdated Jul 2025 | Mar 2025 | granted Jul 2025 | Jul 2025 | North East Lincolnshire | 7.3 |
| Magnolia Streetbattery storage | battery storage | 20 | abandonedupdated Mar 2019 | Sep 2017 | — | Mar 2019 | North East Lincolnshire | 7.5 |
| West Marsh (Phase 1)solar farm | solar farm | 2 | abandonedupdated Jan 2019 | Oct 2014 | granted Feb 2015 | Jan 2019 | North East Lincolnshire | 8.1 |
| Macaulay Lane Solar Farmsolar farm | solar farm | 8 | application withdrawnupdated Sep 2022 | May 2021 | — | Sep 2022 | North East Lincolnshire | 8.1 |
| West Marsh (Phase 2)solar farm | solar farm | 5 | abandonedupdated Jan 2019 | Oct 2014 | granted Feb 2015 | Jan 2019 | North East Lincolnshire | 8.1 |
| Grimsby West, Birchin Wayrooftop solar | rooftop solar | 1.1 | operationalupdated Jan 2024 | Mar 2023 | granted May 2023 | Jan 2024 | North East Lincolnshire | 8.1 |
| Solar Panels at North & S/O Lincoln Gatesolar farm | solar farm | 98 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | East Lindsey | 8.2 |
| HSH Coldstores, Estate Roadrooftop solar | rooftop solar | 1.1 | operationalupdated Jan 2024 | Mar 2023 | granted May 2023 | Jan 2024 | North East Lincolnshire | 8.9 |
| Gunnerby Road - 30MW Battery Energy Storagebattery storage | battery storage | 30 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | North East Lincolnshire | 9.5 |
Smaller schemes under 1 MW, mostly rooftop solar (18)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Weelsby Pumping Station, Hewitts Avenuesolar farm | solar farm | 0.4 | approved, not builtupdated May 2023 | Nov 2022 | granted Apr 2023 | May 2023 | North East Lincolnshire | 2.9 |
| Hewitts Avenue Tescorooftop solar | rooftop solar | 0.5 | operationalupdated Apr 2020 | Dec 2018 | granted Mar 2019 | Apr 2020 | North East Lincolnshire | 3.1 |
| Thorpe Park Holiday Camp, Anthonys Bank Roadrooftop solar | rooftop solar | 0.6 | approved, not built may be out of dateupdated May 2023 | Feb 2023 | granted Apr 2023 | May 2023 | North East Lincolnshire | 3.5 |
| Oasis Academy Wintringhamrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2022 | Feb 2020 | granted Mar 2020 | Jul 2022 | North East Lincolnshire | 4.9 |
| Diana Princess Of Wales Hospitalrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Apr 2026 | Dec 2025 | granted Feb 2026 | Apr 2026 | North East Lincolnshire | 5.2 |
| Grimsby Institute, Laceby Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2022 | Sep 2022 | granted Nov 2022 | Nov 2022 | North East Lincolnshire | 5.8 |
| MRS Coldstore, Norfolk Lanerooftop solar | rooftop solar | 0.5 | refusedupdated Oct 2024 | Feb 2024 | refused Oct 2024 | Oct 2024 | North East Lincolnshire | 6.0 |
| J Sainsbury Plc, Corporation Roadrooftop solar | rooftop solar | 0.5 | application submitted | Jun 2026 | — | — | North East Lincolnshire | 7.2 |
| N H Case Limitedrooftop solar | rooftop solar | 0.4 | under constructionupdated Nov 2021 | Sep 2021 | granted Aug 2022 | Nov 2021 | North East Lincolnshire | 7.4 |
| Murray Street, Grimsby Dockssolar farm | solar farm | 0.8 | approved, not builtupdated Jul 2025 | Mar 2025 | granted Jul 2025 | Jul 2025 | North East Lincolnshire | 7.5 |
| Sea Farm Piggery, Marshchapelrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2025 | Mar 2024 | granted Apr 2024 | Mar 2025 | East Lindsey | 7.6 |
| Freshney Green Primary Care Centre, Sorrel Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | North East Lincolnshire | 7.6 |
| Hilmore Road, Laceby - Photovoltaic Solar Systemrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2022 | Feb 2022 | granted May 2022 | Mar 2022 | North East Lincolnshire | 7.9 |
| Manor Golf Course, Barton Streetsolar farm | solar farm | — | approved, not builtupdated Oct 2024 | Mar 2024 | granted Sep 2024 | Oct 2024 | North East Lincolnshire | 8.2 |
| Estuary Waywind turbine | wind turbine | — | application submitted may be out of dateupdated May 2024 | Apr 2024 | — | May 2024 | North East Lincolnshire | 8.4 |
| Estate Roadrooftop solar | rooftop solar | 0.7 | approved, not built may be out of dateupdated Apr 2022 | Mar 2022 | granted May 2022 | Apr 2022 | North East Lincolnshire | 8.5 |
| Armadillo Self Storage, The Deans, 1 Estate Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jul 2025 | May 2025 | granted Jun 2025 | Jul 2025 | North East Lincolnshire | 9.2 |
| Daniels Chilled Foods, Lakesiderooftop solar | rooftop solar | 0.8 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Jul 2025 | Aug 2025 | North East Lincolnshire | 9.7 |
Distance from the average position of the DN36 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 11 | 1 | 5 | 2 | 0 | 144 |
| Rooftop solar | 16 | 1 | 11 | 3 | 1 | 5 |
| Wind farm | 5 | 0 | 0 | 2 | 2 | 0 |
| Wind turbine | 1 | 1 | 0 | 0 | 0 | 0 |
| Battery storage | 4 | 1 | 2 | 0 | 0 | 89.9 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Humber Gateway A | 219 | operationalupdated Oct 2016 | 38.4 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How North East Lincolnshire decides solar, wind and battery applications
| Applications | North East Lincolnshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 41 | 10,236 |
| Refused | 2 (5%) | 19% |
| Solar refused | 1 of 30 | 12% |
| Onshore wind refused | 0 of 2 | 45% |
| Battery storage refused | 1 of 9 | 16% |
| Median time from submission to decision | 17.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
All projects in North East Lincolnshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DN36, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.