Louth Canal Wind Farm (10 MW)
Louth Canal Wind Farm is a 10 MW wind farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 29 August 2014; the record was last updated on 3 September 2014.
10 MWwind farm
refused on appealstatus in REPD
3 September 2014record last updated
East Lindseycouncil area
Planning timeline
| Date | Stage |
|---|---|
| 26 March 2012 | Application submitted |
| 23 April 2013 | Refused by the planning authority |
| 29 August 2014 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 10 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 3 September 2014
- Operator or applicant
- Partnerships for Renewables
- Planning authority
- East Lindsey
- Planning application reference
- N/133/00586/12
- Appeal reference
- APP/D2510/A/13/2200887
- Turbines
- 4
- Address (REPD)
- Louth Canal, Tetney, Grimsby, Humberside
- Council area (by location)
- East Lindsey
- Time to decision
- 56 weeks
- REPD reference
- 4397
Who decides
| Applications | East Lindsey | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 11 (22%) | 19% |
| Solar refused | 0 of 30 | 12% |
| Onshore wind refused | 11 of 15 | 45% |
| Battery storage refused | 0 of 4 | 16% |
| Median time from submission to decision | 17.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Fen Lane wind farm | wind farm | 17.5 | refused on appeal | 1.6 |
| Bishopthorpe | wind farm | 16.4 | operational | 3.1 |
| Damwells Farm | wind farm | 10 | application withdrawn | 4.4 |
| Solar Panels at North & S/O Lincoln Gate | solar farm | 98 | application submitted | 6.1 |
| Hewitts Avenue, New Waltham | battery storage | 49.9 | approved, not built | 7.1 |
| Fen Farm | wind farm | 16 | operational | 7.9 |
| Yarburgh Grove Farm | solar farm | 8.1 | operational | 8.3 |
| Fen Farm Solar Park | solar farm | 14 | approved, not built | 8.7 |
| Fen Farm Solar Park (extension) | solar farm | 5 | permission expired | 8.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4817, 0.0024).