Bishopthorpe (16.4 MW wind farm)

Bishopthorpe is a 16.4 MW wind farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 January 2017; the record was last updated on 20 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16.4 MWwind farm
operationalstatus in REPD
20 April 2017record last updated
East Lindseycouncil area

Planning timeline

DateStage
2 October 2012Application submitted
5 February 2014Refused by the planning authority
13 February 2014Appeal lodged
20 March 2015Planning permission granted
20 March 2015Secretary of State granted
25 January 2016Construction started
30 January 2017Operational

Project details

Technology
wind farm
Capacity
16.4 MW
Status (REPD)
operational
Record last updated
20 April 2017
Operator or applicant
Greencoat UK (formerly BayWa r.e.)
Planning authority
East Lindsey
Planning application reference
N/178/01969/12
Appeal reference
APP/D2510/A/14/2213150
Turbines
8
Turbine height
115 m
Address (REPD)
Bishopthorpe Farm, Bishopthorpe, Tetney, Grimsby, Humberside
Council area (by location)
East Lindsey
Time to decision
128 weeks
REPD reference
4256

Who decides

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Louth Canal Wind Farmwind farm10refused on appeal3.1
Hewitts Avenue, New Walthambattery storage49.9approved, not built4.5
Fen Lane wind farmwind farm17.5refused on appeal4.7
Damwells Farmwind farm10application withdrawn6.9
Solar Panels at North & S/O Lincoln Gatesolar farm98application submitted8.7
Bradley Road Solar Farmsolar farm43.7approved, not built9.0
Bradley Roadbattery storage10approved, not built9.0
Low Farm Solar Arraysolar farm20operational9.2
Magnolia Streetbattery storage20abandoned9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.5099, -0.0007).