Yarburgh Grove Farm (8.1 MW solar farm)

Yarburgh Grove Farm is an 8.1 MW solar farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 12 November 2015; the record was last updated on 4 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.1 MWsolar farm
operationalstatus in REPD
4 September 2018record last updated
East Lindseycouncil area

Planning timeline

DateStage
21 May 2014Application submitted
20 October 2014Planning permission granted
1 October 2015Construction started
12 November 2015Operational

Project details

Technology
solar farm
Capacity
8.1 MW
Status (REPD)
operational
Record last updated
4 September 2018
Operator or applicant
Foresight
Planning authority
East Lindsey
Planning application reference
N/218/00928/14
Site area
16.8 ha
Address (REPD)
Land rear of Yarburgh Grove Farm, Westfield Road, Yarburgh
Council area (by location)
East Lindsey
Time to decision
22 weeks
REPD reference
2309

Who decides

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fen Farmwind farm16operational3.8
Fen Farm Solar Park (extension)solar farm5permission expired4.5
Fen Farm Solar Parksolar farm14approved, not built4.8
Solar Panels at North & S/O Lincoln Gatesolar farm98application submitted5.8
Damwells Farmwind farm10application withdrawn6.6
Fen Lane wind farmwind farm17.5refused on appeal6.8
Louth Canal Wind Farmwind farm10refused on appeal8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.4075, 0.0188).