Energy Projects Near You

Dudgeon East offshore wind farm

Dudgeon East is a 402 MW offshore wind farm with 67 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 October 2017; the record was last updated on 2 January 2020. Its REPD grid reference is 16 km from the nearest postcode on land (PE31 8AX, King's Lynn and West Norfolk). It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

402 MWoffshore wind farm
operationalstatus in REPD
2 January 2020record last updated
16 km from land (King's Lynn and West Norfolk)REPD location

Consent timeline

DateStage
12 June 2009Application submitted
6 July 2012Section 36 consent granted (Secretary of State)
17 March 2016Construction started
15 October 2017Operational

Project details

Technology
offshore wind farm
Capacity
402 MW
Turbines
67
Turbine capacity
6 MW
Status (REPD)
operational
Record last updated
2 January 2020
Operator or applicant
Statoil / Statkraft
Consenting authority (REPD)
DECC (S36)
Application reference
not recorded
Nearest postcode on land
PE31 8AX (King's Lynn and West Norfolk), 16.0 km from the REPD grid reference
Time to decision
160 weeks
Contracts for Difference
Investment Contract
REPD reference
2538

Who decides

It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Postcode districts within 40 km

Districtkm
Skegness (PE25)19.1
Hunstanton (PE36)21.0
Skegness (PE24)23.9
Wells-Next-the-Sea (NR23)24.9
King's Lynn (PE31)26.3
Walsingham (NR22)29.9
King's Lynn and West Norfolk (PE35)33.0
Alford (LN13)33.0
Mablethorpe (LN12)33.1
Fakenham (NR21)34.6
Spilsby (PE23)35.5
Holt (NR25)38.3

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
Race Bank (Phase 1)290operational2.6
Race Bank (Phase 2)284operational2.6
Westermost Rough A210operational4.1
Centrica (Lincs)270operational10.7
Lynn97.2operational11.0
Inner Dowsing97.2operational13.6
Docking Shoal A540refused14.7
Triton Knoll857operational19.6

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (53.1175, 0.6135).