Bambers Farm (9.6 MW wind farm)

Bambers Farm is a 9.6 MW wind farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 November 2004; the record was last updated on 4 December 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.6 MWwind farm
operationalstatus in REPD
4 December 2009record last updated
East Lindseycouncil area

Planning timeline

DateStage
18 February 2003Application submitted
15 June 2003Planning permission granted
1 November 2004Operational

Project details

Technology
wind farm
Capacity
9.6 MW
Status (REPD)
operational
Record last updated
4 December 2009
Operator or applicant
Ecotricity
Planning authority
East Lindsey
Planning application reference
N/110/00269/03
Turbines
8
Address (REPD)
Mile Lane, Mablethorpe, Lincolnshire
Council area (by location)
East Lindsey
Time to decision
17 weeks
REPD reference
3157

Who decides

ApplicationsEast LindseyUK
Decided applications (solar, wind, battery)4910,236
Refused11 (22%)19%
Solar refused0 of 3012%
Onshore wind refused11 of 1545%
Battery storage refused0 of 416%
Median time from submission to decision17.4 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Asserby wind farmwind farm10refused6.0
Gayton Le Marsh Wind Farmwind farm16.4operational6.7
Langham Wind Farmwind farm12refused on appeal9.2
High Leassolar farm6.5operational9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3213, 0.2384).