Bambers Farm (9.6 MW wind farm)
Bambers Farm is a 9.6 MW wind farm project in East Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 November 2004; the record was last updated on 4 December 2009.
9.6 MWwind farm
operationalstatus in REPD
4 December 2009record last updated
East Lindseycouncil area
Planning timeline
| Date | Stage |
|---|---|
| 18 February 2003 | Application submitted |
| 15 June 2003 | Planning permission granted |
| 1 November 2004 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 9.6 MW
- Status (REPD)
- operational
- Record last updated
- 4 December 2009
- Operator or applicant
- Ecotricity
- Planning authority
- East Lindsey
- Planning application reference
- N/110/00269/03
- Turbines
- 8
- Address (REPD)
- Mile Lane, Mablethorpe, Lincolnshire
- Council area (by location)
- East Lindsey
- Time to decision
- 17 weeks
- REPD reference
- 3157
Who decides
| Applications | East Lindsey | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 49 | 10,236 |
| Refused | 11 (22%) | 19% |
| Solar refused | 0 of 30 | 12% |
| Onshore wind refused | 11 of 15 | 45% |
| Battery storage refused | 0 of 4 | 16% |
| Median time from submission to decision | 17.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Asserby wind farm | wind farm | 10 | refused | 6.0 |
| Gayton Le Marsh Wind Farm | wind farm | 16.4 | operational | 6.7 |
| Langham Wind Farm | wind farm | 12 | refused on appeal | 9.2 |
| High Leas | solar farm | 6.5 | operational | 9.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.3213, 0.2384).