Renewable energy projects in North Norfolk

39 solar, wind or battery projects of 150 kW or more are located in North Norfolk (REPD, July 2026 extract): 0 pending, 19 approved but not running, 14 operational and 2 refused. The council refused 4 of 36 decided applications (11%; UK 19%), with a median 14 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

39projects in the council area
0awaiting a decision
19approved, not running
11%of decisions refused

How North Norfolk decides

ApplicationsNorth NorfolkUK
Decided applications (solar, wind, battery)3610,236
Refused4 (11%)19%
Solar refused2 of 2912%
Onshore wind refused2 of 245%
Battery storage refused0 of 516%
Median time from submission to decision13.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Projects in North Norfolk

Projects of 1 MW and more (25)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Shereford Road, West Raynham Estatebattery storagebattery storage50approved, not builtupdated Dec 2025May 2025granted Nov 2025Dec 2025
West Raynhamsolar farmsolar farm49.9operationalupdated Apr 2015Oct 2013granted Dec 2013Apr 2015
Scottow Moor - RAF Coltishall Solar Farm (Phase 1)solar farmsolar farm32operationalupdated Apr 2017Oct 2014granted Dec 2014Apr 2017
Heydon Road, Heydonsolar farmsolar farm30approved, not builtupdated May 2026Aug 2025granted Apr 2026May 2026
North Creake Airfieldsolar farmsolar farm20operationalupdated Aug 2014Feb 2013granted Mar 2013Aug 2014
Scottow Moor - RAF Coltishall Solar Farm (Phase 2)solar farmsolar farm17.9operationalupdated Apr 2017Oct 2014granted Dec 2014Apr 2017
Scottow Road Solar Farmsolar farmsolar farm12.7application withdrawnupdated Feb 2013Nov 2012—Feb 2013
Belaugh Road Solar Farmsolar farmsolar farm12application withdrawnupdated Jan 2013Nov 2012—Jan 2013
North Norfolk Business Centre Solar Parksolar farmsolar farm11operationalupdated Mar 2018Jul 2012granted Nov 2012Mar 2018
Hall Farm, East Beckhamsolar farmsolar farm10.2operationalupdated Apr 2014Jun 2013granted Sep 2013Apr 2014
Grove Farm (wind)wind farmwind farm6.8refusedupdated Sep 2011Oct 2009refused Nov 2010Sep 2011
North Norfolk Business Centre Solar Park Battery Energy Storage Schemebattery storagebattery storage6operationalupdated Mar 2024Nov 2021granted Dec 2022Mar 2024
Church Farm Solarsolar farmsolar farm5.7application withdrawnupdated Feb 2013Nov 2012—Feb 2013
Carlton Farm Solar farmsolar farmsolar farm5operationalupdated Apr 2012Apr 2011granted May 2011Apr 2012
Frog's Loke Solar Farmsolar farmsolar farm5operationalupdated Jul 2016Jun 2015granted Oct 2015Jul 2016
Bunn's Hill Solar Parksolar farmsolar farm5operationalupdated Aug 2016Jun 2015granted Oct 2015Aug 2016
Wayside Farmsolar farmsolar farm5approved, not built may be out of dateupdated Sep 2020Nov 2015granted Feb 2016Sep 2020
Scottow Solar Farmbattery storagebattery storage4.3approved, not builtupdated Dec 2025Jul 2025granted Nov 2025Dec 2025
Pond Farmsolar farmsolar farm3.6operationalupdated Nov 2014Aug 2013granted Nov 2013Nov 2014
Scottow Estate Wind Farmwind farmwind farm3.6refusedupdated Feb 2014Jan 2013refused Apr 2013Feb 2014
Snettisham Solar Farmsolar farmsolar farm2.7operationalupdated Jun 2017Oct 2014granted Mar 2016Jun 2017
Uphouse Farm - Sandpits Solar Farm & Battery Energy storagesolar farmsolar farm2.4approved, not builtupdated Jul 2025Jan 2025granted Jun 2025Jul 2025
Uphouse Farm - Sandpits Solar Farm & Battery Energy storagebattery storagebattery storage2.4approved, not builtupdated Jul 2025Jan 2025granted Jun 2025Jul 2025
Paston Road, Bactonsolar farmsolar farm1.6approved, not built may be out of dateupdated Jul 2021Sep 2021granted Sep 2022Jul 2021
R And Jm Pace, Church Roadsolar farmsolar farm1.1approved, not built may be out of dateupdated May 2023Jan 2023granted Apr 2023May 2023
Smaller schemes under 1 MW, mostly rooftop solar (14)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Helhoughton Road, Hemptonrooftop solarrooftop solar0.9approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023
Hempton Poultry Sheds, Hempton Roadrooftop solarrooftop solar0.5application withdrawnupdated Sep 2023Jul 2023—Sep 2023
Stody Estate Solar Arraysolar farmsolar farm0.5operationalupdated Apr 2021Nov 2020granted Oct 2021Apr 2021
Bunkers Hill, Wells Roadrooftop solarrooftop solar0.4approved, not builtupdated Jun 2026Apr 2026granted Apr 2026Jun 2026
The Reef Leisure Centrerooftop solarrooftop solar0.4approved, not built may be out of dateupdated Feb 2023Dec 2022granted Jan 2023Feb 2023
Hole Farm House, Hole Farm Roadsolar farmsolar farm0.3approved, not built may be out of dateupdated Mar 2023Jan 2023granted Mar 2023Mar 2023
Laurels Farm, Laurels Roadsolar farmsolar farm0.2approved, not built may be out of dateupdated Mar 2023Oct 2022granted Feb 2023Mar 2023
Victory Swim and Fitness Centre, Station Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024
Barningham Road - Ground Mounted Solar Panelssolar farmsolar farm0.2approved, not built may be out of dateupdated May 2023Feb 2023granted May 2023May 2023
Back Lane, Hempsteadsolar farmsolar farm0.2approved, not built may be out of dateupdated Jun 2023Feb 2023granted Jun 2023Jun 2023
Plumstead Road, Edgefieldsolar farmsolar farm0.2approved, not built may be out of dateupdated May 2023Feb 2023granted May 2023May 2023
H M Prison Burerooftop solarrooftop solar0.2operationalupdated Mar 2021Apr 2020granted Jun 2020Mar 2021
Cromer Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Apr 2024Feb 2024granted Apr 2024Apr 2024
Holt Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2023Mar 2023granted May 2023May 2023

Postcode districts in North Norfolk

DistrictProjects within 10 kmPendingApprovedOperational
NR1117168
NR1218067
NR2110054
NR226023
NR233012
NR2411063
NR258053
NR2610064
NR277034
NR2815156

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to North Norfolk by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.