Energy Projects Near You

Grove Farm (wind) (6.8 MW)

Grove Farm (wind) is a 6.8 MW wind farm project in North Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 25 November 2010; the record was last updated on 13 September 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.8 MWwind farm
refusedstatus in REPD
13 September 2011record last updated
North Norfolkcouncil area

Planning timeline

DateStage
27 October 2009Application submitted
25 November 2010Refused by the planning authority

Project details

Technology
wind farm
Capacity
6.8 MW
Status (REPD)
refused
Record last updated
13 September 2011
Operator or applicant
Private Developer
Planning authority
North Norfolk
Planning application reference
PF/09/1060
Turbines
2
Address (REPD)
Ingham, Brumstead, Norfolk
Council area (by location)
North Norfolk
Time to decision
56 weeks
REPD reference
2766

Who decides

ApplicationsNorth NorfolkUK
Decided applications (solar, wind, battery)3610,236
Refused4 (11%)19%
Solar refused2 of 2912%
Onshore wind refused2 of 245%
Battery storage refused0 of 516%
Median time from submission to decision13.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bunn's Hill Solar Parksolar farm5operational8.8
Frog's Loke Solar Farmsolar farm5operational8.8
Carlton Farm Solar farmsolar farm5operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7862, 1.5279).