Hall Farm, East Beckham (10.2 MW solar farm)
Hall Farm, East Beckham is a 10.2 MW solar farm project in North Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 30 April 2014.
10.2 MWsolar farm
operationalstatus in REPD
30 April 2014record last updated
North Norfolkcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 27 June 2013 | Application submitted |
| 23 September 2013 | Planning permission granted |
| 31 March 2014 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 10.2 MW
- Status (REPD)
- operational
- Record last updated
- 30 April 2014
- Operator or applicant
- TGC Renewables
- Planning authority
- North Norfolk
- Planning application reference
- PF/13/0772
- Site area
- 24.9 ha
- Address (REPD)
- Hall Farm, Land At Hall Farm, East Beckham, Holt, Norfolk, BR11 8GA
- Council area (by location)
- North Norfolk
- Time to decision
- 13 weeks
- REPD reference
- 1329
Who decides
| Applications | North Norfolk | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 36 | 10,236 |
| Refused | 4 (11%) | 19% |
| Solar refused | 2 of 29 | 12% |
| Onshore wind refused | 2 of 2 | 45% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 13.7 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| North Norfolk Business Centre Solar Park | solar farm | 11 | operational | 8.2 |
| North Norfolk Business Centre Solar Park Battery Energy Storage Scheme | battery storage | 6 | operational | 8.3 |
| Church Farm Solar | solar farm | 5.7 | application withdrawn | 9.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9134, 1.1868).