North Norfolk Business Centre Solar Park Battery Energy Storage Scheme (6 MW)

North Norfolk Business Centre Solar Park Battery Energy Storage Scheme is a 6 MW battery storage project in North Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational; the record was last updated on 20 March 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWbattery storage
operationalstatus in REPD
20 March 2024record last updated
North Norfolkcouncil area

Planning timeline

DateStage
23 November 2021Application submitted
19 December 2022Planning permission granted

Project details

Technology
battery storage (co-located with re)
Capacity
6 MW
Status (REPD)
operational
Record last updated
20 March 2024
Operator or applicant
Next Energy
Planning authority
North Norfolk
Planning application reference
PF/21/3122
Address (REPD)
Manor Farm Crossdale Street Northrepps Cromer
Council area (by location)
North Norfolk
Time to decision
56 weeks
Name in REPD
North Norfolk Business Centre Solar Park - Battery Energy Storage Scheme
REPD reference
10497

Recorded together with North Norfolk Business Centre Solar Park (11 MW solar farm, operational).

Who decides

ApplicationsNorth NorfolkUK
Decided applications (solar, wind, battery)3610,236
Refused4 (11%)19%
Solar refused2 of 2912%
Onshore wind refused2 of 245%
Battery storage refused0 of 516%
Median time from submission to decision13.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hall Farm, East Beckhamsolar farm10.2operational8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9012, 1.3083).