Energy Projects Near You

Scottow Moor - RAF Coltishall Solar Farm (Phase 2) (17.9 MW)

Scottow Moor - RAF Coltishall Solar Farm (Phase 2) is a 17.9 MW solar farm project in North Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 March 2016; the record was last updated on 4 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17.9 MWsolar farm
operationalstatus in REPD
4 April 2017record last updated
North Norfolkcouncil area

Planning timeline

DateStage
9 October 2014Application submitted
23 December 2014Planning permission granted
25 January 2016Construction started
29 March 2016Operational

Project details

Technology
solar farm
Capacity
17.9 MW
Status (REPD)
operational
Record last updated
4 April 2017
Operator or applicant
Greencoat Capital
Planning authority
North Norfolk
Planning application reference
PF/14/1334
Address (REPD)
Former RAF Coltishall, Coltishall Airfield, Filby Road, Norwich, Norfolk
Council area (by location)
North Norfolk
Time to decision
11 weeks
REPD reference
5199

Who decides

ApplicationsNorth NorfolkUK
Decided applications (solar, wind, battery)3610,236
Refused4 (11%)19%
Solar refused2 of 2912%
Onshore wind refused2 of 245%
Battery storage refused0 of 516%
Median time from submission to decision13.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Scottow Moor - RAF Coltishall Solar Farm (Phase 1)solar farm32operational<0.1
Scottow Road Solar Farmsolar farm12.7application withdrawn1.4
Land off Belaugh Roadsolar farm12application withdrawn4.8
Belaugh Road Solar Farmsolar farm12application withdrawn5.0
Bunn's Hill Solar Parksolar farm5operational5.6
Frog's Loke Solar Farmsolar farm5operational5.6
Carlton Farm Solar farmsolar farm5operational6.2
Wayside Farmsolar farm5approved, not built6.2
Burgate Solar Farmsolar farm15approved, not built6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7551, 1.3569).