Energy Projects Near You

Solar, wind and battery projects near Norwich (NR10)

19 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NR10 (Broadland): 1 is waiting for a planning decision, 9 approved but not yet running, 4 operational. The largest live scheme is Docking Farm Solar (28 MW solar farm, approved on 11 February 2022, not yet built; REPD status may be out of date), 7.5 km away. Offshore, 1 wind farm is recorded within 40 km; the nearest is Scroby Sands (60 MW, operational), 38.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19projects within 10 km
1awaiting a decision
9approved, not running
4operational

Projects within 10 km of NR10

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Burgate Solar Farmsolar farmsolar farm15approved, not builtupdated Nov 2022Oct 2020granted Aug 2021Nov 2022Broadland5.4
Glebe Horsford Solar Farmsolar farmsolar farm18approved, not builtupdated Feb 2026Aug 2023granted Jul 2025Feb 2026Broadland6.0
Warren Wood Energy Park Solar Farm & Battery Energy Storagesolar farmsolar farm25refusedupdated Apr 2026May 2025refused Dec 2025Apr 2026Broadland6.3
Warren Wood Energy Park Solar Farm & Battery Energy Storagebattery storagebattery storage10refusedupdated Apr 2026May 2025refused Dec 2025Apr 2026Broadland6.3
Hall Road, Alderfordsolar farmsolar farm28refusedupdated May 2026Jul 2025refused Mar 2026May 2026Broadland7.2
Docking Farm Solarsolar farmsolar farm28approved, not built may be out of dateupdated Feb 2024Jul 2021granted Feb 2022Feb 2024Broadland7.5
Scottow Solar Farmbattery storagebattery storage4.3approved, not builtupdated Dec 2025Jul 2025granted Nov 2025Dec 2025North Norfolk7.7
Oulton Airfield Solar Farm (Phase 1)solar farmsolar farm5operationalupdated Jul 2016Jun 2015granted Sep 2015Jul 2016Broadland7.8
Scottow Road Solar Farmsolar farmsolar farm12.7application withdrawnupdated Feb 2013Nov 2012—Feb 2013North Norfolk8.1
Scottow Moor - RAF Coltishall Solar Farm (Phase 1)solar farmsolar farm32operationalupdated Apr 2017Oct 2014granted Dec 2014Apr 2017North Norfolk8.1
Scottow Moor - RAF Coltishall Solar Farm (Phase 2)solar farmsolar farm17.9operationalupdated Apr 2017Oct 2014granted Dec 2014Apr 2017North Norfolk8.1
Scottow Estate Wind Farmwind farmwind farm3.6refusedupdated Feb 2014Jan 2013refused Apr 2013Feb 2014North Norfolk9.3
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Burgh Road, Aylsham - Micro Battery Storagebattery storagebattery storage0.2application submittedMay 2026——Broadland6.5
Docking Farm Solarbattery storagebattery storage—approved, not built may be out of dateupdated Feb 2024Jul 2021granted Feb 2022Feb 2024Broadland7.5
Klyne Business Aviation Centre, Buck Courtney Crescentrooftop solarrooftop solar0.5approved, not builtupdated Sep 2023Aug 2023granted Sep 2023Sep 2023Norwich7.5
Tc Fines, Norwich Roadsolar farmsolar farm0.5approved, not builtupdated Sep 2023Jan 2023granted Aug 2023Sep 2023Broadland7.6
H M Prison Burerooftop solarrooftop solar0.2operationalupdated Mar 2021Apr 2020granted Jun 2020Mar 2021North Norfolk7.6
Fluke Calibration, Hurricane Wayrooftop solarrooftop solar0.5approved, not builtupdated Jan 2025Sep 2024granted Dec 2024Jan 2025Norwich7.9
Bannatyne Health Club, Ernest Gage Avenuerooftop solarrooftop solar0.2approved, not builtupdated Aug 2024Jun 2024granted Jul 2024Aug 2024South Norfolk9.7

Distance from the average position of the NR10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm10043261.5
Rooftop solar403101.2
Wind farm100010
Battery storage412014.5

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Scroby Sands60operationalupdated Feb 201638.3

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Broadland decides solar, wind and battery applications

ApplicationsBroadlandUK
Decided applications (solar, wind, battery)2210,236
Refused7 (32%)19%
Solar refused4 of 1712%
Onshore wind refused2 of 245%
Battery storage refused1 of 316%
Median time from submission to decision18.3 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

All projects in Broadland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NR10, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.