Energy Projects Near You

Warren Wood Energy Park Solar Farm & Battery Energy Storage (25 MW)

Warren Wood Energy Park Solar Farm & Battery Energy Storage is a 25 MW solar farm project in Broadland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 5 December 2025; the record was last updated on 8 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
refusedstatus in REPD
8 April 2026record last updated
Broadlandcouncil area

Planning timeline

DateStage
20 May 2025Application submitted
5 December 2025Refused by the planning authority

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
refused
Record last updated
8 April 2026
Operator or applicant
Exagen Development Limited
Planning authority
Broadland
Planning application reference
2025/1531
Site area
96.0 ha
Address (REPD)
N/O Aylsham Road, Cawston, Norwich
Council area (by location)
Broadland
Time to decision
28 weeks
Name in REPD
Warren Wood Energy Park - Solar Farm & Battery Energy Storage
REPD reference
18333

The scheme also includes 10 MW of battery storage, recorded separately in REPD (refused).

Who decides

ApplicationsBroadlandUK
Decided applications (solar, wind, battery)2210,236
Refused7 (32%)19%
Solar refused4 of 1712%
Onshore wind refused2 of 245%
Battery storage refused1 of 316%
Median time from submission to decision18.3 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Docking Farm Solarsolar farm28approved, not built2.7
Oulton Airfield Solar Farm (Phase 1)solar farm5operational3.3
Hall Road, Alderfordsolar farm28refused5.5
Heydon Road, Heydonsolar farm30approved, not built5.9
Nowhere Lane, Norwichsolar farm40approved, not built6.1
Church Farm Solarsolar farm5.7application withdrawn7.0
Guestwickwind farm12refused8.2
Woodforde Farmsolar farm9operational9.5
The Old Airfieldsolar farm5operational9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.77, 1.1657).