Energy Projects Near You

Glebe Horsford Solar Farm (18 MW)

Glebe Horsford Solar Farm is an 18 MW solar farm project in Broadland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 1 July 2025, not yet built; the record was last updated on 23 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWsolar farm
approved, not builtstatus in REPD
23 February 2026record last updated
Broadlandcouncil area

Planning timeline

DateStage
9 August 2023Application submitted
22 August 2024Refused by the planning authority
25 February 2025Appeal lodged
1 July 2025Planning permission granted
1 July 2025Appeal allowed
1 July 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
18 MW
Status (REPD)
approved, not built
Record last updated
23 February 2026
Operator or applicant
Pathfinder Clean Energy UKDev Limited
Planning authority
Broadland
Planning application reference
2023/2395
Appeal reference
APP/K2610/W/25/3359225
Site area
35.6 ha
Address (REPD)
North East of Reepham Road,Horsford
Council area (by location)
Broadland
Time to decision
99 weeks
Contracts for Difference
AR7a
Name in REPD
Glebe Horsford - Solar Farm
REPD reference
12646

Who decides

ApplicationsBroadlandUK
Decided applications (solar, wind, battery)2210,236
Refused7 (32%)19%
Solar refused4 of 1712%
Onshore wind refused2 of 245%
Battery storage refused1 of 316%
Median time from submission to decision18.3 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Burgate Solar Farmsolar farm15approved, not built5.2
New Road Solar Farmsolar farm5under construction5.7
Hall Road, Alderfordsolar farm28refused8.5
The Old Airfieldsolar farm5operational9.3
White Horse Lane (Trowse) - Phase 2solar farm9approved, not built9.6
Land East of White Horse Lanesolar farm5operational9.6
Mulbarton Road, Keswickbattery storage400application submitted9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6817, 1.2411).