Energy Projects Near You

New Road Solar Farm (5 MW)

New Road Solar Farm is a 5 MW solar farm project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 December 2016; the record was last updated on 23 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
under constructionstatus in REPD
23 September 2020record last updated
South Norfolkcouncil area

Planning timeline

DateStage
23 July 2015Application submitted
2 November 2015Planning permission granted
1 December 2016Construction started

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
under construction
Record last updated
23 September 2020
Operator or applicant
Solar Century/ Bluefield Solar
Planning authority
South Norfolk
Planning application reference
2015/1678
Site area
9.4 ha
Address (REPD)
Land Adj A47 And North Of, New Road, Bawburgh, Norwich
Council area (by location)
South Norfolk
Time to decision
15 weeks
REPD reference
5543

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Glebe Horsford Solar Farmsolar farm18approved, not built5.7
Mulbarton Road, Keswickbattery storage400application submitted7.0
Colton Solar photovoltaic farm, Battery storagesolar farm30under construction7.3
Colton Solar photovoltaic farm, Battery storagebattery storage30under construction7.3
Hornsea Project Threebattery storage300under construction7.8
Land East of White Horse Lanesolar farm5operational8.2
White Horse Lane (Trowse) - Phase 2solar farm9approved, not built8.2
Hall Farm, Hickling Lanebattery storage400application submitted8.3
Bracon Ash Solarsolar farm28.5under construction8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6383, 1.1975).