Energy Projects Near You

Hornsea Project Three (300 MW battery storage)

Hornsea Project Three is a 300 MW battery storage project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 December 2025; the record was last updated on 9 July 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

300 MWbattery storage
under constructionstatus in REPD
9 July 2026record last updated
South Norfolkcouncil area

Planning timeline

DateStage
26 April 2022Application submitted
23 January 2023Planning permission granted
1 December 2025Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
300 MW
Status (REPD)
under construction
Record last updated
9 July 2026
Operator or applicant
Orsted Power (UK) Limited
Planning authority
South Norfolk
Planning application reference
2022/0867
Address (REPD)
E/O Main Road, Swardeston
Council area (by location)
South Norfolk
Time to decision
39 weeks
Name in REPD
Hornsea Project Three - Battery Storage
REPD reference
9754

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hall Farm, Hickling Lanebattery storage400application submitted0.7
Hickling Lane, Swainsthorpe -Battery Storagebattery storage114approved, not built1.9
Norwich Substation Storage Facilitybattery storage49.9approved, not built1.9
Stoke Lanebattery storage130approved, not built2.3
Land south of Brick Kiln Roadsolar farm5operational2.5
Bracon Ash Solarsolar farm28.5under construction2.9
Bloy’s Grove Solar Farmsolar farm49.9approved, not built2.9
Mulbarton Road, Keswickbattery storage400application submitted3.0
Flordon Road, Bracon Ash Solar Panels & Battery Storagesolar farm24approved, not built3.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5754, 1.2473).