Flordon Road, Bracon Ash Solar Panels & Battery Storage (24 MW)

Flordon Road, Bracon Ash Solar Panels & Battery Storage is a 24 MW solar farm project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 July 2025, not yet built; the record was last updated on 23 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWsolar farm
approved, not builtstatus in REPD
23 June 2026record last updated
South Norfolkcouncil area

Planning timeline

DateStage
18 April 2023Application submitted
4 July 2025Planning permission granted

Project details

Technology
solar farm
Capacity
24 MW
Status (REPD)
approved, not built
Record last updated
23 June 2026
Operator or applicant
Ralos Projects Limited
Planning authority
South Norfolk
Planning application reference
2023/1055
Site area
28.9 ha
Address (REPD)
Land Off Marsh Lane Bracon Ash
Council area (by location)
South Norfolk
Time to decision
115 weeks
Name in REPD
Flordon Road, Bracon Ash - Solar Panels & Battery Storage
REPD reference
14307

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wymondham Road, Bracon Ashbattery storage228application submitted0.8
Bracon Ash Solarsolar farm28.5under construction2.0
Land south of Brick Kiln Roadsolar farm5operational2.2
Bloy’s Grove Solar Farmsolar farm49.9approved, not built3.2
Hornsea Project Threebattery storage300under construction3.9
Lotus Manufacturingwind farm6refused3.9
Hall Farm, Hickling Lanebattery storage400application submitted4.0
Stoke Lanebattery storage130approved, not built4.6
Norwich Substation Storage Facilitybattery storage49.9approved, not built4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5443, 1.2208).