Energy Projects Near You

Norwich Substation Storage Facility (49.9 MW)

Norwich Substation Storage Facility is a 49.9 MW battery storage project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 November 2018, not yet built; the record was last updated on 17 September 2020. REPD also records that the planning permission expired on 15 November 2021, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtmay be out of datestatus in REPD
17 September 2020record last updated
South Norfolkcouncil area

REPD also records that the planning permission expired on 15 November 2021, so the project may not go ahead in this form.

Planning timeline

DateStage
9 November 2018Application submitted
15 November 2018Planning permission granted
15 November 2021Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
17 September 2020
Operator or applicant
Pivot Power
Planning authority
South Norfolk
Planning application reference
2018/2017
Address (REPD)
Norwich Main Substation, Mangreen Hall Lane, Dunston, Norwich, Norfolk
Council area (by location)
South Norfolk
Time to decision
1 weeks
REPD reference
7021

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hickling Lane, Swainsthorpe -Battery Storagebattery storage114approved, not built<0.1
Stoke Lanebattery storage130approved, not built0.9
Hall Farm, Hickling Lanebattery storage400application submitted1.3
Hornsea Project Threebattery storage300under construction1.9
Bloy’s Grove Solar Farmsolar farm49.9approved, not built2.5
Mulbarton Road, Keswickbattery storage400application submitted2.5
Land south of Brick Kiln Roadsolar farm5operational2.9
White Horse Lane (Trowse) - Phase 2solar farm9approved, not built4.1
Land East of White Horse Lanesolar farm5operational4.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5735, 1.2757).