Energy Projects Near You

Bloy’s Grove Solar Farm (49.9 MW)

Bloy’s Grove Solar Farm is a 49.9 MW solar farm project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 August 2022, not yet built; the record was last updated on 11 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
11 September 2025record last updated
South Norfolkcouncil area

Planning timeline

DateStage
9 November 2021Application submitted
4 August 2022Planning permission granted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
11 September 2025
Operator or applicant
EDF Energy Renewables
Planning authority
South Norfolk
Planning application reference
2021/2495
Site area
79.6 ha
Address (REPD)
Kiln Lane, Swainsthorpe, Norwich
Council area (by location)
South Norfolk
Time to decision
38 weeks
REPD reference
8308

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land south of Brick Kiln Roadsolar farm5operational1.2
Stoke Lanebattery storage130approved, not built1.7
Hickling Lane, Swainsthorpe -Battery Storagebattery storage114approved, not built2.5
Norwich Substation Storage Facilitybattery storage49.9approved, not built2.5
Hall Farm, Hickling Lanebattery storage400application submitted2.5
Hornsea Project Threebattery storage300under construction2.9
Flordon Road, Bracon Ash Solar Panels & Battery Storagesolar farm24approved, not built3.2
Wymondham Road, Bracon Ashbattery storage228application submitted3.9
Bracon Ash Solarsolar farm28.5under construction3.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5519, 1.2671).