Energy Projects Near You

Hickling Lane, Swainsthorpe -Battery Storage (114 MW)

Hickling Lane, Swainsthorpe -Battery Storage is a 114 MW battery storage project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 September 2023, not yet built; the record was last updated on 18 September 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

114 MWbattery storage
approved, not builtstatus in REPD
18 September 2023record last updated
South Norfolkcouncil area

Planning timeline

DateStage
9 March 2023Application submitted
13 September 2023Planning permission granted
13 September 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
114 MW
Status (REPD)
approved, not built
Record last updated
18 September 2023
Operator or applicant
EDF Energy Renewables
Planning authority
South Norfolk
Planning application reference
2023/0617
Address (REPD)
Land North Of Hickling Lane Swainsthorpe
Council area (by location)
South Norfolk
Time to decision
27 weeks
REPD reference
13560

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Norwich Substation Storage Facilitybattery storage49.9approved, not built<0.1
Stoke Lanebattery storage130approved, not built0.9
Hall Farm, Hickling Lanebattery storage400application submitted1.3
Hornsea Project Threebattery storage300under construction1.9
Bloy’s Grove Solar Farmsolar farm49.9approved, not built2.5
Mulbarton Road, Keswickbattery storage400application submitted2.5
Land south of Brick Kiln Roadsolar farm5operational2.9
White Horse Lane (Trowse) - Phase 2solar farm9approved, not built4.1
Land East of White Horse Lanesolar farm5operational4.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5735, 1.2757).