Land south of Brick Kiln Road (5 MW solar farm)

Land south of Brick Kiln Road is a 5 MW solar farm project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 17 March 2016; the record was last updated on 18 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
18 August 2016record last updated
South Norfolkcouncil area

Planning timeline

DateStage
4 June 2015Application submitted
3 September 2015Planning permission granted
18 January 2016Construction started
17 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
18 August 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
South Norfolk
Planning application reference
2015/1221
Site area
10.2 ha
Address (REPD)
Land South Of, Brick Kiln Road, Mulbarton, Norwich, Norfolk
Council area (by location)
South Norfolk
Time to decision
13 weeks
REPD reference
5285

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bloy’s Grove Solar Farmsolar farm49.9approved, not built1.2
Flordon Road, Bracon Ash Solar Panels & Battery Storagesolar farm24approved, not built2.2
Hall Farm, Hickling Lanebattery storage400application submitted2.3
Stoke Lanebattery storage130approved, not built2.4
Hornsea Project Threebattery storage300under construction2.5
Bracon Ash Solarsolar farm28.5under construction2.8
Wymondham Road, Bracon Ashbattery storage228application submitted2.9
Norwich Substation Storage Facilitybattery storage49.9approved, not built2.9
Hickling Lane, Swainsthorpe -Battery Storagebattery storage114approved, not built2.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5526, 1.2496).