Energy Projects Near You

Bracon Ash Solar (28.5 MW)

Bracon Ash Solar is a 28.5 MW solar farm project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 November 2023; the record was last updated on 21 December 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28.5 MWsolar farm
under constructionstatus in REPD
21 December 2021record last updated
South Norfolkcouncil area

Planning timeline

DateStage
12 March 2021Application submitted
21 December 2021Planning permission granted
1 November 2023Construction started

Project details

Technology
solar farm
Capacity
28.5 MW
Status (REPD)
under construction
Record last updated
21 December 2021
Operator or applicant
Luminous Energy Ltd
Planning authority
South Norfolk
Planning application reference
2021/0569
Site area
32.2 ha
Address (REPD)
Land East Of, Cranes Road, Hethel, Norwich, Norfolk
Council area (by location)
South Norfolk
Time to decision
41 weeks
Contracts for Difference
AR5
REPD reference
8148

The scheme also includes battery storage, recorded separately in REPD (under construction).

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Flordon Road, Bracon Ash Solar Panels & Battery Storagesolar farm24approved, not built2.0
Wymondham Road, Bracon Ashbattery storage228application submitted2.6
Lotus Manufacturingwind farm6refused2.7
Land south of Brick Kiln Roadsolar farm5operational2.8
Hornsea Project Threebattery storage300under construction2.9
Hall Farm, Hickling Lanebattery storage400application submitted3.3
Bloy’s Grove Solar Farmsolar farm49.9approved, not built3.9
Stoke Lanebattery storage130approved, not built4.5
Hickling Lane, Swainsthorpe -Battery Storagebattery storage114approved, not built4.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5616, 1.2116).