Solar, wind and battery projects near Wymondham (NR18)
29 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NR18 (South Norfolk): 4 are waiting for a planning decision, 17 approved but not yet running, 5 operational. The largest live scheme is Hall Farm, Hickling Lane (400 MW battery storage, application submitted on 16 December 2024, no decision recorded), 9.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of NR18
Projects of 1 MW and more (19)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Lotus Manufacturingwind farm | wind farm | 6 | refusedupdated Jun 2011 | Jun 2007 | refused Oct 2007 | Jun 2011 | South Norfolk | 4.3 |
| Rookery Business Parksolar farm | solar farm | 5 | operationalupdated Aug 2016 | May 2015 | granted Sep 2015 | Aug 2016 | South Norfolk | 4.9 |
| Baileys Meadow Solar Farmsolar farm | solar farm | 5 | refusedupdated Aug 2011 | Feb 2011 | refused Aug 2011 | Aug 2011 | Breckland | 5.5 |
| Hardingham Solar Farmsolar farm | solar farm | 14.8 | operationalupdated Feb 2014 | Oct 2012 | granted Dec 2012 | Feb 2014 | Breckland | 6.2 |
| Hardingham Solar Farm - extensionsolar farm | solar farm | 5.2 | operationalupdated Jan 2017 | May 2014 | granted Oct 2014 | Jan 2017 | Breckland | 6.4 |
| Bracon Ash Solarsolar farm | solar farm | 28.5 | under constructionupdated Dec 2021 | Mar 2021 | granted Dec 2021 | Dec 2021 | South Norfolk | 7.0 |
| Barnham Broom Hotel and Golf Clubsolar farm | solar farm | 1 | application submitted may be out of dateupdated Sep 2020 | Aug 2020 | — | Sep 2020 | South Norfolk | 7.8 |
| Wymondham Road, Bracon Ashbattery storage | battery storage | 228 | application submittedupdated May 2025 | Mar 2025 | — | May 2025 | South Norfolk | 8.0 |
| Flordon Road, Bracon Ash Solar Panels & Battery Storagesolar farm | solar farm | 24 | approved, not builtupdated Jun 2026 | Apr 2023 | granted Jul 2025 | Jun 2026 | South Norfolk | 8.1 |
| Colton Road, Barnham Broomsolar farm | solar farm | 1 | approved, not builtupdated May 2025 | Nov 2024 | granted Apr 2025 | May 2025 | South Norfolk | 8.2 |
| Colton Solar photovoltaic farm, Battery storagesolar farm | solar farm | 30 | under constructionupdated Feb 2026 | Mar 2022 | granted Jun 2022 | Feb 2026 | South Norfolk | 8.6 |
| Colton Solar photovoltaic farm, Battery storagebattery storage | battery storage | 30 | under constructionupdated Feb 2026 | Mar 2022 | granted Jun 2022 | Feb 2026 | South Norfolk | 8.6 |
| Hornsea Project Threebattery storage | battery storage | 300 | under constructionupdated Jul 2026 | Apr 2022 | granted Jan 2023 | Jul 2026 | South Norfolk | 9.3 |
| New Road Solar Farmsolar farm | solar farm | 5 | under constructionupdated Sep 2020 | Jul 2015 | granted Nov 2015 | Sep 2020 | South Norfolk | 9.6 |
| Land south of Brick Kiln Roadsolar farm | solar farm | 5 | operationalupdated Aug 2016 | Jun 2015 | granted Sep 2015 | Aug 2016 | South Norfolk | 9.7 |
| Tas Valleysolar | solar | 1.2 | application withdrawnupdated Oct 2014 | Mar 2014 | — | Oct 2014 | South Norfolk | 9.7 |
| Land North of the A11 Solar Parksolar farm | solar farm | 1 | approved, not built may be out of dateupdated Nov 2021 | Nov 2021 | granted Oct 2022 | Nov 2021 | Breckland | 9.8 |
| Attleborough Road Solar Farmsolar farm | solar farm | 30 | under constructionupdated Feb 2026 | Feb 2021 | granted Oct 2021 | Feb 2026 | Breckland | 9.9 |
| Hall Farm, Hickling Lanebattery storage | battery storage | 400 | application submittedupdated Jan 2025 | Dec 2024 | — | Jan 2025 | South Norfolk | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (10)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Wymondham Leisure Centre, Norwich Roadrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Oct 2022 | Sep 2022 | — | Oct 2022 | South Norfolk | 0.7 |
| Wymondham Leisure Centre, Norwich Roadbattery storage | battery storage | 0.3 | approved, not builtupdated Mar 2025 | Oct 2024 | granted Feb 2025 | Mar 2025 | South Norfolk | 0.8 |
| Wymondham Leisure Centre, Norwich Road -Solar Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2025 | Oct 2024 | granted Feb 2025 | Mar 2025 | South Norfolk | 0.8 |
| Lotus Cars, Potash Lanerooftop solar | rooftop solar | 1 | approved, not builtupdated Jan 2023 | Nov 2022 | granted Dec 2022 | Jan 2023 | South Norfolk | 4.9 |
| The Everest Systembattery storage | battery storage | 0.1 | operationalupdated Nov 2016 | Feb 2008 | — | Nov 2016 | South Norfolk | 4.9 |
| Mindful Snacker, Little Melton Food Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2025 | Aug 2025 | granted Sep 2025 | Oct 2025 | South Norfolk | 6.6 |
| Bracon Ash Solarbattery storage | battery storage | — | under constructionupdated Jul 2024 | Mar 2021 | granted Dec 2021 | Jul 2024 | South Norfolk | 7.0 |
| Flordon Road, Bracon Ash Solar Panels & Battery Storagebattery storage | battery storage | — | approved, not builtupdated Jun 2026 | Apr 2023 | granted Jul 2025 | Jun 2026 | South Norfolk | 8.1 |
| Field Trials Station, Sparrows Hillrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2026 | Mar 2026 | granted Apr 2026 | Jun 2026 | South Norfolk | 8.1 |
| Honingham Thorpe Farm, Norwich Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2022 | Aug 2022 | granted Sep 2022 | Sep 2022 | Broadland | 8.4 |
Distance from the average position of the NR18 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 13 | 1 | 7 | 4 | 1 | 120 |
| Rooftop solar | 6 | 1 | 5 | 0 | 0 | 2.3 |
| Solar | 1 | 0 | 0 | 0 | 0 | 0 |
| Wind farm | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 8 | 2 | 5 | 1 | 0 | 958 |
MW in pipeline: pending, approved and under-construction capacity.
How South Norfolk decides solar, wind and battery applications
| Applications | South Norfolk | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 50 | 10,236 |
| Refused | 8 (16%) | 19% |
| Solar refused | 1 of 30 | 12% |
| Onshore wind refused | 7 of 7 | 45% |
| Battery storage refused | 0 of 13 | 16% |
| Median time from submission to decision | 20.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NR18, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.