Rookery Business Park (5 MW solar farm)

Rookery Business Park is a 5 MW solar farm project in South Norfolk, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 11 February 2016; the record was last updated on 31 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
31 August 2016record last updated
South Norfolkcouncil area

Planning timeline

DateStage
29 May 2015Application submitted
3 September 2015Planning permission granted
11 December 2015Construction started
11 February 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
31 August 2016
Operator or applicant
Solar Century/ Bluefield Solar
Planning authority
South Norfolk
Planning application reference
2015/1215
Site area
9.1 ha
Address (REPD)
Land adjacent to Rookery Busin, Silver Street, Besthorpe
Council area (by location)
South Norfolk
Time to decision
14 weeks
REPD reference
5296

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Attleborough Road Solar Farmsolar farm30under construction4.9
Baileys Meadow Solar Farmsolar farm5refused7.2
Lotus Manufacturingwind farm6refused7.7
Hardingham Solar Farm - extensionsolar farm5.2operational7.9
Hardingham Solar Farmsolar farm14.8operational7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5353, 1.0661).