Hardingham Solar Farm (14.8 MW)

Hardingham Solar Farm is a 14.8 MW solar farm project in Breckland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 5 January 2014; the record was last updated on 6 February 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.8 MWsolar farm
operationalstatus in REPD
6 February 2014record last updated
Brecklandcouncil area

Planning timeline

DateStage
1 October 2012Application submitted
21 December 2012Planning permission granted
5 January 2014Operational

Project details

Technology
solar farm
Capacity
14.8 MW
Status (REPD)
operational
Record last updated
6 February 2014
Operator or applicant
Solar Century/ Bluefield Solar
Planning authority
Breckland
Planning application reference
3PL/2012/1021/F
Address (REPD)
Hardingham
Council area (by location)
Breckland
Time to decision
12 weeks
REPD reference
1223

Who decides

ApplicationsBrecklandUK
Decided applications (solar, wind, battery)3810,236
Refused7 (18%)19%
Solar refused4 of 2812%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision19.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hardingham Solar Farm - extensionsolar farm5.2operational0.3
Baileys Meadow Solar Farmsolar farm5refused0.8
Colton Solar photovoltaic farm, Battery storagebattery storage30under construction6.1
Colton Solar photovoltaic farm, Battery storagesolar farm30under construction6.1
Rookery Business Parksolar farm5operational7.9
The Park Farm, Birds Cornersolar farm49.9application submitted8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6041, 1.0351).