Hardingham Solar Farm - extension (5.2 MW)

Hardingham Solar Farm - extension is a 5.2 MW solar farm project in Breckland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 February 2015; the record was last updated on 16 January 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.2 MWsolar farm
operationalstatus in REPD
16 January 2017record last updated
Brecklandcouncil area

Planning timeline

DateStage
23 May 2014Application submitted
28 October 2014Planning permission granted
3 December 2014Construction started
19 February 2015Operational

Project details

Technology
solar farm
Capacity
5.2 MW
Status (REPD)
operational
Record last updated
16 January 2017
Operator or applicant
Solar Century/ Bluefield Solar
Planning authority
Breckland
Planning application reference
3PL/2014/0545/F
Site area
11.7 ha
Address (REPD)
Land to the East of Hardingham
Council area (by location)
Breckland
Time to decision
23 weeks
REPD reference
2300

Who decides

ApplicationsBrecklandUK
Decided applications (solar, wind, battery)3810,236
Refused7 (18%)19%
Solar refused4 of 2812%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision19.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hardingham Solar Farmsolar farm14.8operational0.3
Baileys Meadow Solar Farmsolar farm5refused0.9
Colton Solar photovoltaic farm, Battery storagesolar farm30under construction6.3
Colton Solar photovoltaic farm, Battery storagebattery storage30under construction6.3
Rookery Business Parksolar farm5operational7.9
The Park Farm, Birds Cornersolar farm49.9application submitted8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6032, 1.0304).