Energy Projects Near You

Baileys Meadow Solar Farm (5 MW)

Baileys Meadow Solar Farm is a 5 MW solar farm project in Breckland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 18 August 2011; the record was last updated on 24 August 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refusedstatus in REPD
24 August 2011record last updated
Brecklandcouncil area

Planning timeline

DateStage
8 February 2011Application submitted
18 August 2011Refused by the planning authority

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
24 August 2011
Operator or applicant
Alectron Investments
Planning authority
South Norfolk
Planning application reference
2011/0202
Site area
17.8 ha
Address (REPD)
Hardingham, Norwich, Norfolk
Council area (by location)
Breckland
Time to decision
27 weeks
REPD reference
1043

Who decides

ApplicationsSouth NorfolkUK
Decided applications (solar, wind, battery)5010,236
Refused8 (16%)19%
Solar refused1 of 3012%
Onshore wind refused7 of 745%
Battery storage refused0 of 1316%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hardingham Solar Farmsolar farm14.8operational0.8
Hardingham Solar Farm - extensionsolar farm5.2operational0.9
Colton Solar photovoltaic farm, Battery storagebattery storage30under construction6.4
Colton Solar photovoltaic farm, Battery storagesolar farm30under construction6.4
Rookery Business Parksolar farm5operational7.2
The Park Farm, Birds Cornersolar farm49.9application submitted9.1
Lotus Manufacturingwind farm6refused9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5979, 1.0408).