Energy Projects Near You

Solar, wind and battery projects near Norwich (NR16)

9 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NR16 (Breckland): 2 are waiting for a planning decision, 4 approved but not yet running, 3 operational. The largest live scheme is Market Lane And Carr Lane, Great Moulton (400 MW battery storage, application submitted on 6 June 2025, no decision recorded), 8.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9projects within 10 km
2awaiting a decision
4approved, not running
3operational

Projects within 10 km of NR16

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Attleborough Road Solar Farmsolar farmsolar farm30under constructionupdated Feb 2026Feb 2021granted Oct 2021Feb 2026Breckland3.1
Kenninghall Solar / Hazeldick Solarsolar farmsolar farm8operationalupdated May 2015Oct 2012granted Sep 2014May 2015Breckland6.1
Land North of the A11 Solar Parksolar farmsolar farm1approved, not built may be out of dateupdated Nov 2021Nov 2021granted Oct 2022Nov 2021Breckland6.5
Airfield Farm PVsolar farmsolar farm5operationalupdated Mar 2013Nov 2010granted Jan 2011Mar 2013Breckland6.9
Rookery Business Parksolar farmsolar farm5operationalupdated Aug 2016May 2015granted Sep 2015Aug 2016South Norfolk7.0
Market Lane And Carr Lane, Great Moultonbattery storagebattery storage400application submittedupdated Jul 2025Jun 2025—Jul 2025South Norfolk8.9
Farmers Industrial Estate,Mill Road Solar PV Systemssolar farmsolar farm1.2approved, not builtupdated Apr 2024Apr 2023granted Apr 2024Apr 2024South Norfolk9.2
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hargham Roadsolar farmsolar farm0.2application submitted may be out of dateupdated Apr 2024Mar 2024—Apr 2024Breckland4.6
IFD Group, Harling Roadrooftop solarrooftop solar0.2approved, not builtupdated Jun 2023Jan 2023granted Feb 2023Jun 2023Breckland6.3

Distance from the average position of the NR16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm7133032.5
Rooftop solar101000.2
Battery storage11000400

MW in pipeline: pending, approved and under-construction capacity.

How Breckland decides solar, wind and battery applications

ApplicationsBrecklandUK
Decided applications (solar, wind, battery)3810,236
Refused7 (18%)19%
Solar refused4 of 2812%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision19.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Breckland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NR16, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.