Energy Projects Near You

Kenninghall Solar / Hazeldick Solar (8 MW)

Kenninghall Solar / Hazeldick Solar is an 8 MW solar farm project in Breckland, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 28 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWsolar farm
operationalstatus in REPD
28 May 2015record last updated
Brecklandcouncil area

Planning timeline

DateStage
17 October 2012Application submitted
3 October 2013Refused by the planning authority
10 January 2014Appeal lodged
24 September 2014Planning permission granted
24 September 2014Appeal allowed
1 January 2015Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
28 May 2015
Operator or applicant
Norfolk Renewables
Planning authority
Breckland
Planning application reference
3PL/2012/1088/F
Appeal reference
APP/F2605/W/13/2211560
Address (REPD)
Land to the west of Kenninghall
Council area (by location)
Breckland
Time to decision
101 weeks
REPD reference
5231

Who decides

ApplicationsBrecklandUK
Decided applications (solar, wind, battery)3810,236
Refused7 (18%)19%
Solar refused4 of 2812%
Onshore wind refused3 of 745%
Battery storage refused0 of 316%
Median time from submission to decision19.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitebreads Farmsolar farm10refused4.8
Airfield Farm PVsolar farm5operational5.4
Attleborough Road Solar Farmsolar farm30under construction7.6
Hall Farm and Field Barn Farmsolar farm34refused8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4329, 0.9909).