Scroby Sands offshore wind farm

Scroby Sands is a 60 MW offshore wind farm with 30 turbines in English waters. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2004; the record was last updated on 29 February 2016. Its REPD grid reference is 4 km from the nearest postcode on land (NR30 5DJ, Great Yarmouth). It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60 MWoffshore wind farm
operationalstatus in REPD
29 February 2016record last updated
4 km from land (Great Yarmouth)REPD location

Consent timeline

DateStage
5 March 2001Application submitted
1 December 2002Section 36 consent granted (Secretary of State)
1 October 2003Construction started
1 March 2004Operational

Project details

Technology
offshore wind farm
Capacity
60 MW
Turbines
30
Turbine capacity
2 MW
Status (REPD)
operational
Record last updated
29 February 2016
Operator or applicant
E.ON UK
Consenting authority (REPD)
DECC (S36)
Application reference
not recorded
Nearest postcode on land
NR30 5DJ (Great Yarmouth), 3.7 km from the REPD grid reference
Time to decision
91 weeks
REPD reference
2498

Who decides

It was consented under Section 36 of the Electricity Act 1989 by the Secretary of State for energy (REPD: DECC, the energy department at the time).

Postcode districts within 40 km

Districtkm
Great Yarmouth (NR30)4.9
Great Yarmouth (NR31)9.4
Great Yarmouth (NR29)11.7
Lowestoft (NR32)17.6
Lowestoft (NR33)21.7
Norwich (NR13)22.0
Norwich (NR12)25.0
Beccles (NR34)26.7
Norwich (NR14)29.3
Norwich (NR7)30.6
Bungay (NR35)31.4
Norwich (NR1)32.6

Straight-line distance from the centre of each postcode district to the REPD grid reference of the wind farm, which is a single point for the whole site.

Other offshore wind projects within 30 km

ProjectMWStatuskm
East Anglia 2 (EA 2)900approved, not built27.0

All offshore wind farms in UK waters

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database can lag behind consent decisions. Location: REPD grid reference (52.6439, 1.7889).